ITAC Assessment: UF0520
ITAC logo
ITAC Assessment: UF0520
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Terpene Resins
NAICS 325211: Plastics Material and Resin Manufacturing
SIC 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers
Sales Range $10
M
to 50
M
# of Employees 18
Plant Area 150,000
ft2
Annual Production 16,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $148,561 2,537,613
kWh
Electricity Demand $78,434 5,148
kW-mo/yr
Electricity Fees $36,846 -
Natural Gas $77,533 13,923
MMBtu
Other Energy $212,806 23,422
MMBtu
Waste Disposal Costs
Water Usage $75,538 18,744
Tgal
TOTAL YEARLY COSTS $629,718
RECOMMENDED SAVINGS* $307,535 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $82,624

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Energy Savings Administrative Changes Savings By-product Production Savings
01 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $219,545 $970,000 $152,100
2,600,000
kWh
$73,133
-
kW-mo/yr
$(-119,912.0)
-
MMBtu
$114,224
-
MMBtu
- -
02 2.2427: Use waste heat from hot flue gases to preheat incoming fluids $4,699 $15,000 - - $4,699
-
MMBtu
- - -
03 2.2522: Isolate hot or cold equipment $5,366 $5,125 $5,366
91,728
kWh
- - - - -
04 2.3212: Optimize plant power factor $1,303 $2,207 - - - - $1,303 -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,084 $1,020 $722
12,355
kWh
$362
-
kW-mo/yr
- - - -
06 3.6114: Use precipitating agents in waste water treatment that produce the least quantity of waste $75,538 $33,400 - - - - - $75,538
TOTAL RECOMMENDED $307,535 $1,026,752 $158,188
2,704,083
kWh
$73,495
-
kW-mo/yr
$(-115,213.0)
-
MMBtu
$114,224
-
MMBtu
$1,303 $75,538
TOTAL IMPLEMENTED $82,624 $51,627 $722
12,355
kWh
$362
-
kW-mo/yr
$4,699
-
MMBtu
- $1,303 $75,538
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Energy Savings Administrative Changes Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs