Assessment Year | 2017 |
---|---|
Principal Product | Apple and Citrus Flavors |
NAICS | 311423: Dried and Dehydrated Food Manufacturing |
SIC | 2034: Dried and Dehydrated Fruits, Vegetables, and Soup Mixes |
Sales Range | $10 M to 50M |
# of Employees | 54 |
Plant Area |
49,295
ft2
|
Annual Production | 26,566,000
lb
|
Production Hrs. Annual | 4,992
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $106,099 | 1,837,840 |
kWh
|
$0.058 | |
Electricity Demand | $37,833 | 4,855 |
kW-mo/yr
|
$7.79 | |
Electricity Fees | $23,802 | - |
|
- | |
Natural Gas | $75,908 | 10,608 |
MMBtu
|
$7.16 | |
Waste Disposal Costs | |||||
Water Usage | $15,192 | 4,157 |
Tgal
|
$3.65 | |
TOTAL YEARLY COSTS | $258,835 | ||||
RECOMMENDED SAVINGS* | $103,314 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $58,802 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1224: Replace boiler | $38,664 | $30,000 | - | - |
$38,664
-
MMBtu
|
- | |
02 | 2.2522: Isolate hot or cold equipment | $25,893 | $3,150 |
$25,893
454,272
kWh
|
- | - | - | |
03 | 2.7232: Replace existing hvac unit with high efficiency model | $14,487 | $23,157 |
$14,487
254,160
kWh
|
- | - | - | |
04 | 2.2312: Minimize non-essential material in heat treatment process | $7,542 | - | - | - |
$3,798
-
MMBtu
|
$3,744 | |
05 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $6,342 | $27,695 |
$6,342
111,266
kWh
|
- | - | - | |
06 | 2.4133: Use most efficient type of electric motors | $5,848 | $10,386 |
$4,265
74,821
kWh
|
$1,583
-
kW-mo/yr
|
- | - | |
07 | 2.2136: Install / repair insulation on steam lines | $2,443 | $1,481 | - | - |
$2,443
-
MMBtu
|
- | |
08 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,095 | $5,053 |
$2,095
36,757
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $103,314 | $100,922 |
$53,082
931,276
kWh
|
$1,583
-
kW-mo/yr
|
$44,905
-
MMBtu
|
$3,744 | ||
TOTAL IMPLEMENTED | $58,802 | $60,536 |
$48,817
856,455
kWh
|
- |
$6,241
-
MMBtu
|
$3,744 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs