ITAC Assessment: UF0452
ITAC logo
ITAC Assessment: UF0452
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Cement
NAICS 327310: Cement Manufacturing
SIC 3241: Cement, Hydraulic
Sales Range $100
M
to 500
M
# of Employees 27
Plant Area 130,000
ft2
Annual Production 160,000
ton
Production Hrs. Annual 4,992
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $975,698 14,989,098
kWh
Electricity Demand $240,308 64,200
kW-mo/yr
Natural Gas $198,131 46,394
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,746 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2511: Insulate bare equipment $11,846 $20,077 - - $11,846
-
MMBtu
02 2.6218: Turn off equipment when not in use $12,308 - $12,308
189,354
kWh
- -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,797 $8,904 $4,711
72,480
kWh
$86
-
kW-mo/yr
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,408 - $3,408
52,442
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $7,387 $7,579 $7,301
112,320
kWh
$86
-
kW-mo/yr
-
TOTAL RECOMMENDED $39,746 $36,560 $27,728
426,596
kWh
$172
-
kW-mo/yr
$11,846
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs