ITAC Assessment: UF0445
ITAC logo
ITAC Assessment: UF0445
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product citrus oil
NAICS 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing
SIC 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 40
Plant Area 40,000
ft2
Annual Production 20,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $121,959 1,666,240
kWh
Electricity Demand $43,927 3,587
kW-mo/yr
LPG $213,226 11,113
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $221,521 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $50,139

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Solid Waste (non-haz) Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $13,864 $4,542 $11,304
152,753
kWh
$2,561
-
kW-mo/yr
- -
02 2.7121: Utilize daylight whenever possible in lieu of artificial light $5,543 $9,823 $3,071
41,496
kWh
$2,472
-
kW-mo/yr
- -
03 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $1,693 $939 $1,693
17,064
kWh
- - -
04 2.2622: Replace existing chiller with high efficiency model $25,323 $75,000 $25,323
253,225
kWh
- - -
05 2.2136: Install / repair insulation on steam lines $43,678 $2,580 - - $43,678
-
MMBtu
-
06 2.4323: Use optimum size and capacity equipment $2,582 $2,580 $2,582
25,815
kWh
- - -
07 2.4113: Install motor voltage controller on lightly loaded motors $802 $1,378 $802
8,028
kWh
- - -
08 2.4133: Use most efficient type of electric motors $735 $1,280 $735
9,802
kWh
- - -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,370 $8,778 $8,370
88,102
kWh
- - -
10 2.1336: Install equipment to utilize waste fuel $118,931 $150,000 - - - $118,931
-
lb
TOTAL RECOMMENDED $221,521 $256,900 $53,879
596,285
kWh
$5,033
-
kW-mo/yr
$43,678
-
MMBtu
$118,931
-
lb
TOTAL IMPLEMENTED $50,139 $90,900 $47,579
519,895
kWh
$2,561
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs