Assessment Year | 2010 |
---|---|
Principal Product | aircraft ignition exciters |
NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3694: Electrical Equipment for Internal Combustion Engines |
Sales Range | $5 M to 10M |
# of Employees | 600 |
Plant Area |
150,000
ft2
|
Annual Production | 10,000
units
|
Production Hrs. Annual | 4,860
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $861,099 | 7,854,933 |
kWh
|
$0.11 |
Electricity Demand | $160,799 | 17,766 |
kW-mo/yr
|
$9.05 |
Electricity Fees | $65,259 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $135,699 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $46,408 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $28,959 | $5,655 |
$28,959
288,288
kWh
|
- | |
02 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,044 | - |
$1,044
12,000
kWh
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,531 | - |
$1,531
14,051
kWh
|
- | |
04 | 2.7124: Make a practice of turning off lights when not needed | $2,547 | - |
$2,547
29,285
kWh
|
- | |
05 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,211 | - |
$1,211
13,925
kWh
|
- | |
06 | 2.2441: Preheat boiler makeup water with waste process heat | $86,549 | $4,000 | - |
$86,549
-
MMBtu
|
|
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,016 | $404 |
$7,016
64,366
kWh
|
- | |
08 | 2.7228: Avoid introducing hot, humid, or dirty air into hvac system | $6,842 | - |
$6,842
62,779
kWh
|
- | |
TOTAL RECOMMENDED | $135,699 | $10,059 |
$49,150
484,694
kWh
|
$86,549
-
MMBtu
|
||
TOTAL IMPLEMENTED | $46,408 | $6,059 |
$46,408
456,718
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs