| Assessment Year | 2009 |
|---|---|
| Principal Product | pharmaceuticals |
| NAICS | 339112: Surgical and Medical Instrument Manufacturing |
| SIC | 3851: Ophthalmic Goods |
| Sales Range | $100 M to 500M |
| # of Employees | 400 |
| Plant Area |
130,000
ft2
|
| Annual Production | 40,000,000
pieces
|
| Production Hrs. Annual | 6,300
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,550,749 | 16,982,280 |
kWh
|
$0.091 |
| Natural Gas | $397,396 | 36,441 |
MMBtu
|
$10.91 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $340,192 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | By-product Production Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $36,890 | $904 |
$36,890
405,374
kWh
|
- | - | |
| 02 | 2.7135: Install occupancy sensors | $2,358 | - |
$2,358
3,240
kWh
|
- | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,291 | - |
$1,291
14,195
kWh
|
- | - | |
| 04 | 2.6212: Turn off equipment during breaks, reduce operating time | $490 | - |
$490
6,287
kWh
|
- | - | |
| 05 | 2.3212: Optimize plant power factor | $2,671 | $3,405 |
$2,671
-
kWh
|
- | - | |
| 06 | 2.7135: Install occupancy sensors | $32,995 | $9,325 |
$32,995
423,019
kWh
|
- | - | |
| 07 | 2.2511: Insulate bare equipment | $112,051 | $1,026 | - |
$112,051
-
MMBtu
|
- | |
| 08 | 2.7425: Clean or color roof to reduce solar load | $107,292 | $42,500 |
$107,292
1,375,547
kWh
|
- | - | |
| 09 | 2.2441: Preheat boiler makeup water with waste process heat | $41,483 | $4,000 |
$41,483
180,359
kWh
|
- | - | |
| 10 | 3.1293: Separate treatments for each type of solution and recycle | $2,671 | $3,405 | - | - | $2,671 | |
| TOTAL RECOMMENDED | $340,192 | $64,565 |
$225,470
2,408,021
kWh
|
$112,051
-
MMBtu
|
$2,671 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | By-product Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs