Assessment Year | 2008 |
---|---|
Principal Product | Aluminun A/C Distributors |
NAICS | 333415: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipmen |
SIC | 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment |
Sales Range | $10 M to 50M |
# of Employees | 211 |
Plant Area |
236,600
ft2
|
Annual Production | 300,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $499,011 | 4,588,800 |
kWh
|
$0.11 |
Electricity Demand | $64,678 | 902 |
kW-mo/yr
|
$71.71 |
Electricity Fees | $49,622 | - |
|
- |
LPG | $343,512 | 18,379 |
MMBtu
|
$18.69 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $344,333 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $204,871 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $1,719 | $4,557 |
$1,418
11,620
kWh
|
$301
-
kW-mo/yr
|
- | |
02 | 2.7243: Improve air circulation with destratification fans / other methods | $47,620 | $6,301 |
$43,680
233,381
kWh
|
$3,940
-
kW-mo/yr
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $36,287 | $40,292 |
$31,874
261,290
kWh
|
$4,413
-
kW-mo/yr
|
- | |
04 | 2.7141: Lower light fixtures in high ceiling areas | $3,258 | $461 |
$2,863
23,460
kWh
|
$395
-
kW-mo/yr
|
- | |
05 | 2.7135: Install occupancy sensors | $1,200 | $215 |
$1,200
9,850
kWh
|
- | - | |
06 | 2.2437: Recover waste heat from equipment | $888 | $364 | - | - |
$888
-
MMBtu
|
|
07 | 2.2437: Recover waste heat from equipment | $62,348 | $20,000 | - | - |
$62,348
-
MMBtu
|
|
08 | 2.2437: Recover waste heat from equipment | $1,520 | $1,000 | - | - |
$1,520
-
MMBtu
|
|
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $53,144 | $426 |
$53,144
390,763
kWh
|
- | - | |
10 | 2.7226: Use computer programs to optimize hvac performance | $10,946 | $25,280 |
$10,946
89,725
kWh
|
- | - | |
11 | 4.426: Modify workload | $8,002 | - |
$8,002
65,590
kWh
|
- | - | |
12 | 2.2437: Recover waste heat from equipment | $6,419 | $3,400 | - | - |
$6,419
-
MMBtu
|
|
13 | 2.4322: Use or replace with energy efficient substitutes | $110,982 | - | - | - |
$110,982
-
MMBtu
|
|
TOTAL RECOMMENDED | $344,333 | $102,296 |
$153,127
1,085,679
kWh
|
$9,049
-
kW-mo/yr
|
$182,157
-
MMBtu
|
||
TOTAL IMPLEMENTED | $204,871 | $41,394 |
$89,081
685,363
kWh
|
$4,808
-
kW-mo/yr
|
$110,982
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs