Assessment Year | 2007 |
---|---|
Principal Product | Reinforced hoses and rubber seals |
NAICS | 326291: Rubber Product Manufacturing for Mechanical Use |
SIC | 3061: Molded, Extruded, and Lathe-Cut Mechanical Rubber Goods |
Sales Range | $10 M to 50M |
# of Employees | 175 |
Plant Area |
86,000
ft2
|
Annual Production | 8,700,000
pieces
|
Production Hrs. Annual | 4,290
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $337,825 | 7,107,200 |
kWh
|
$0.048 |
Electricity Demand | $146,889 | 15,580 |
kW-mo/yr
|
$9.43 |
Natural Gas | $17,136 | 20,563 |
MMBtu
|
$0.83 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $84,125 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,982 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,913 | $36,935 |
$2,643
110,256
kWh
|
$5,270
-
kW-mo/yr
|
- | - | - | |
02 | 2.7145: Install skylights | $6,200 | $14,564 |
$2,992
62,578
kWh
|
$3,208
-
kW-mo/yr
|
- | - | - | |
03 | 2.7124: Make a practice of turning off lights when not needed | $3,038 | - |
$1,871
38,938
kWh
|
$1,167
-
kW-mo/yr
|
- | - | - | |
04 | 2.2136: Install / repair insulation on steam lines | $1,673 | $2,571 |
$1,673
41,913
kWh
|
- | - | - | - | |
05 | 3.1181: Eliminate a by-product | $3,032 | $158 | - | - |
$3,032
-
MMBtu
|
- | - | |
06 | 4.424: Improve space comfort conditioning | $13,160 | $26,800 |
$13,160
105,848
kWh
|
- | - | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,239 | $638 |
$2,239
46,162
kWh
|
- | - | - | - | |
08 | 4.111: Add equipment/ operators to reduce production bottleneck | $5,850 | $957 | - | - | - | $5,850 | - | |
09 | 4.445: Install equipment to move product | $32,175 | $1,260 | - | - | - | $32,175 | - | |
10 | 4.445: Install equipment to move product | $8,845 | $43,500 | - | - | - | - | $8,845 | |
TOTAL RECOMMENDED | $84,125 | $127,383 |
$24,578
405,695
kWh
|
$9,645
-
kW-mo/yr
|
$3,032
-
MMBtu
|
$38,025 | $8,845 | ||
TOTAL IMPLEMENTED | $9,982 | $3,367 |
$5,783
127,013
kWh
|
$1,167
-
kW-mo/yr
|
$3,032
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs