| Assessment Year | 2005 |
|---|---|
| Principal Product | Brake Hose Assemblies |
| NAICS | 332912: Fluid Power Valve and Hose Fitting Manufacturing |
| SIC | 3492: Fluid Power Valves and Hose Fittings |
| Sales Range | $10 M to 50M |
| # of Employees | 220 |
| Plant Area |
135,000
ft2
|
| Annual Production | 3,000,000
pieces
|
| Production Hrs. Annual | 6,885
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $387,315 | 6,480,002 |
kWh
|
$0.060 |
| Electricity Demand | $77,976 | 1,083 |
kW-mo/yr
|
$72.00 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $92,177 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $78,316 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $18,471 | $1,124 |
$18,471
307,853
kWh
|
- | - | |
| 02 | 2.6218: Turn off equipment when not in use | $1,366 | - |
$1,366
30,354
kWh
|
- | - | |
| 03 | 2.7135: Install occupancy sensors | $13,109 | $1,327 |
$13,109
218,478
kWh
|
- | - | |
| 04 | 2.4133: Use most efficient type of electric motors | $1,178 | $1,272 |
$1,178
18,875
kWh
|
- | - | |
| 05 | 2.7292: Lower ceiling to reduce conditioned space | $15,306 | $1,300 |
$15,306
340,128
kWh
|
- | - | |
| 06 | 2.7229: Air condition only space necessary | $13,549 | $36,650 |
$13,549
225,821
kWh
|
- | - | |
| 07 | 3.5318: Recycle fluorescent lamps | $312 | $3,496 | - | - | $312 | |
| 08 | 4.111: Add equipment/ operators to reduce production bottleneck | $2,448 | $954 | - | - | $2,448 | |
| 09 | 4.424: Improve space comfort conditioning | $26,438 | $1,500 | - | $26,438 | - | |
| TOTAL RECOMMENDED | $92,177 | $47,623 |
$62,979
1,141,509
kWh
|
$26,438 | $2,760 | ||
| TOTAL IMPLEMENTED | $78,316 | $7,477 |
$49,430
915,688
kWh
|
$26,438 | $2,448 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs