ITAC Assessment: UF0365
ITAC logo
ITAC Assessment: UF0365
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Acrylic and Glass Block Windows
NAICS 327211: Flat Glass Manufacturing
SIC 3231: Glass Products, Made of Purchased Glass
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 58,200
ft2
Annual Production 55,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $127,459 2,335,693
kWh
Electricity Demand $35,773 5,993
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,249 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,982

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7134: Use photocell controls $4,861 $2,070 $2,419
62,026
kWh
$2,441
-
kW-mo/yr
02 2.7141: Lower light fixtures in high ceiling areas $3,910 $1,245 $2,706
69,389
kWh
$1,204
-
kW-mo/yr
03 2.7145: Install skylights $3,628 $9,645 $2,081
53,352
kWh
$1,547
-
kW-mo/yr
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,178 $565 $2,178
39,591
kWh
-
05 2.7131: Add area lighting switches $1,633 $6,615 $1,633
41,867
kWh
-
06 2.7124: Make a practice of turning off lights when not needed $1,277 - $1,277
23,212
kWh
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $1,236 $6,602 $827
21,215
kWh
$408
-
kW-mo/yr
08 4.424: Improve space comfort conditioning $2,528 $8,978 $86
2,215
kWh
$2,441
-
kW-mo/yr
TOTAL RECOMMENDED $21,249 $35,720 $13,207
312,867
kWh
$8,042
-
kW-mo/yr
TOTAL IMPLEMENTED $5,982 $9,543 $3,541
65,018
kWh
$2,441
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs