ITAC Assessment: UF0349
ITAC logo
ITAC Assessment: UF0349
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Fertilizer
NAICS 325320: Pesticide and Other Agricultural Chemical Manufacturing
SIC 2879: Pesticides and Agricultural Chemicals, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 14
Plant Area 20,000
ft2
Annual Production 10,000
lb
Production Hrs. Annual 6,600
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $74,995 1,785,600
kWh
Other Energy $108,414 18,069
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,129 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4133: Use most efficient type of electric motors $3,789 $10,863 $3,789
90,217
kWh
02 2.7131: Add area lighting switches $1,188 $6,111 $1,188
28,278
kWh
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,231 $4,583 $1,231
29,311
kWh
04 2.7121: Utilize daylight whenever possible in lieu of artificial light $1,922 $9,158 $1,922
45,751
kWh
TOTAL RECOMMENDED $8,129 $30,715 $8,129
193,557
kWh
TOTAL IMPLEMENTED - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs