Assessment Year | 2004 |
---|---|
Principal Product | Pesticides and Herbicides |
NAICS | 325320: Pesticide and Other Agricultural Chemical Manufacturing |
SIC | 2879: Pesticides and Agricultural Chemicals, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 46 |
Plant Area |
1,000,000
ft2
|
Annual Production | 34,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $485,210 | 14,159,834 |
kWh
|
$0.034 |
Electricity Demand | $117,021 | 26,751 |
kW-mo/yr
|
$4.37 |
Natural Gas | $1,848,123 | 325,697 |
MMBtu
|
$5.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,417,891 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,403,105 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3416: Use combined cycle gas turbine generator sets with waste heat boilers connected to turbine exhaust | $1,333,121 | $2,700,000 |
$893,520
26,280,000
kWh
|
$157,320
-
kW-mo/yr
|
$336,281
-
MMBtu
|
$(-54,000.0) | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,420 | $29,400 |
$7,892
232,131
kWh
|
$2,528
-
kW-mo/yr
|
- | - | |
03 | 2.6218: Turn off equipment when not in use | $7,249 | - |
$5,361
157,680
kWh
|
$1,888
-
kW-mo/yr
|
- | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,169 | $10,500 |
$3,157
92,843
kWh
|
$1,012
-
kW-mo/yr
|
- | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,420 | $22,100 |
$7,892
232,131
kWh
|
$2,528
-
kW-mo/yr
|
- | - | |
06 | 2.4131: Size electric motors for peak operating efficiency | $39,206 | $74,000 |
$29,699
873,503
kWh
|
$9,507
-
kW-mo/yr
|
- | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,366 | - |
$4,366
101,539
kWh
|
- | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,203 | $6,441 |
$1,694
49,814
kWh
|
$509
-
kW-mo/yr
|
- | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,977 | $456 |
$2,994
69,627
kWh
|
- | - | $(-17.0) | |
10 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $3,760 | - |
$2,360
69,420
kWh
|
$1,400
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $1,417,891 | $2,842,897 |
$958,935
28,158,688
kWh
|
$176,692
-
kW-mo/yr
|
$336,281
-
MMBtu
|
$(-54,017.0) | ||
TOTAL IMPLEMENTED | $1,403,105 | $2,820,797 |
$946,677
27,825,018
kWh
|
$174,164
-
kW-mo/yr
|
$336,281
-
MMBtu
|
$(-54,017.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs