| Assessment Year | 2004 |
|---|---|
| Principal Product | Lumber, Wooden Poles |
| NAICS | 321114: Wood Preservation |
| SIC | 2491: Wood Preserving |
| Sales Range | $50 M to 100M |
| # of Employees | 68 |
| Plant Area |
17,500
ft2
|
| Annual Production | 24,000,000
thousand feet
|
| Production Hrs. Annual | 2,470
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $181,220 | 3,391,890 |
kWh
|
$0.053 |
| Electricity Demand | $37,917 | 5,482 |
kW-mo/yr
|
$6.92 |
| Wood | $60,278 | 2,691 |
MMBtu
|
$22.40 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $294,864 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $234,107 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2135: Repair and eliminate steam leaks | $10,952 | $225 | - | - |
$10,952
-
MMBtu
|
- | |
| 02 | 2.2123: Insulate feedwater tank | $1,477 | $1,828 | - | - |
$1,477
-
MMBtu
|
- | |
| 03 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,420 | - |
$872
15,857
kWh
|
$548
-
kW-mo/yr
|
- | - | |
| 04 | 2.2135: Repair and eliminate steam leaks | $4,592 | $1,706 | - | - |
$4,592
-
MMBtu
|
- | |
| 05 | 4.652: Replace existing equipment with more suitable substitutes | $172,708 | $330,000 | - | - | - | $172,708 | |
| 06 | 4.651: Install back-up equipment | $26,182 | $64,000 | - | - | - | $26,182 | |
| 07 | 4.448: Install automatic part storage / retreval system | $59,280 | $260,000 | - | - | - | $59,280 | |
| 08 | 4.652: Replace existing equipment with more suitable substitutes | $13,200 | $12,000 | - | - | - | $13,200 | |
| 09 | 4.812: Apply for investment incentives | $5,053 | $60 | - | - | - | $5,053 | |
| TOTAL RECOMMENDED | $294,864 | $669,819 |
$872
15,857
kWh
|
$548
-
kW-mo/yr
|
$17,021
-
MMBtu
|
$276,423 | ||
| TOTAL IMPLEMENTED | $234,107 | $407,991 |
$872
15,857
kWh
|
$548
-
kW-mo/yr
|
$15,544
-
MMBtu
|
$217,143 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs