ITAC Assessment: DL0119
ITAC logo
ITAC Assessment: DL0119
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Power and Steam
NAICS 221330: Steam and Air-Conditioning Supply
SIC 4961: Steam and Air-Conditioning Supply
Sales Range $500
k
to 1
M
# of Employees 10
Plant Area 999,999
ft2
Annual Production 0
units
Production Hrs. Annual 8,760
hrs
Location (State) Maryland

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $781,227 13,020,442
kWh
Natural Gas $2,629,868 568,006
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $180,545 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Other Liquid (non-haz) Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $74,490 $34,000 $21,893
313,676
kWh
$52,597
-
MMBtu
-
02 2.2441: Preheat boiler makeup water with waste process heat $45,282 $138,000 - $45,282
-
MMBtu
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $35,978 $95,000 $35,978
536,978
kWh
- -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $13,382 $20,000 $13,382
209,100
kWh
- -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $5,947 $3,000 $5,947
88,767
kWh
- -
06 2.4314: Use synthetic lubricant $5,466 $1,000 $3,866
56,800
kWh
- $1,600
-
gal
TOTAL RECOMMENDED $180,545 $291,000 $81,066
1,205,321
kWh
$97,879
-
MMBtu
$1,600
-
gal
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Other Liquid (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs