| Assessment Year | 2013 |
|---|---|
| Principal Product | Power and Steam |
| NAICS | 221330: Steam and Air-Conditioning Supply |
| SIC | 4961: Steam and Air-Conditioning Supply |
| Sales Range | $500 k to 1M |
| # of Employees | 10 |
| Plant Area |
999,999
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Maryland |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $781,227 | 13,020,442 |
kWh
|
$0.060 |
| Natural Gas | $2,629,868 | 568,006 |
MMBtu
|
$4.63 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $180,545 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Liquid (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $74,490 | $34,000 |
$21,893
313,676
kWh
|
$52,597
-
MMBtu
|
- | |
| 02 | 2.2441: Preheat boiler makeup water with waste process heat | $45,282 | $138,000 | - |
$45,282
-
MMBtu
|
- | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $35,978 | $95,000 |
$35,978
536,978
kWh
|
- | - | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $13,382 | $20,000 |
$13,382
209,100
kWh
|
- | - | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,947 | $3,000 |
$5,947
88,767
kWh
|
- | - | |
| 06 | 2.4314: Use synthetic lubricant | $5,466 | $1,000 |
$3,866
56,800
kWh
|
- |
$1,600
-
gal
|
|
| TOTAL RECOMMENDED | $180,545 | $291,000 |
$81,066
1,205,321
kWh
|
$97,879
-
MMBtu
|
$1,600
-
gal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs