Assessment Year | 2003 |
---|---|
Principal Product | Rubber Hoses |
NAICS | 326220: Rubber and Plastics Hoses and Belting Manufacturing |
SIC | 3052: Rubber and Plastics Hose and Belting |
Sales Range | $50 M to 100M |
# of Employees | 550 |
Plant Area |
424,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $139,737 | 415,987 |
kWh
|
$0.34 |
Natural Gas | $14,297 | 280,325 |
MMBtu
|
$0.051 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $161,951 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $161,951 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $19,397 | $57,060 |
$14,297
280,325
kWh
|
$5,100
-
kW-mo/yr
|
- | - | - | |
02 | 2.7132: Install timers on light switches in little used areas | $1,095 | $2,128 |
$1,095
16,589
kWh
|
- | - | - | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $13,612 | - |
$10,775
211,283
kWh
|
- | - | $1,131 | $1,706 | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,681 | $376 |
$11,700
177,276
kWh
|
- | - | $(-19.0) | - | |
05 | 3.1294: Segregate spent solvents and reuse in subsequent washings | $33,833 | $43,600 | - | - |
$33,833
-
gal
|
- | - | |
06 | 4.652: Replace existing equipment with more suitable substitutes | $82,333 | $168,000 | - | - | - | $82,333 | - | |
TOTAL RECOMMENDED | $161,951 | $271,164 |
$37,867
685,473
kWh
|
$5,100
-
kW-mo/yr
|
$33,833
-
gal
|
$83,445 | $1,706 | ||
TOTAL IMPLEMENTED | $161,951 | $271,164 |
$37,867
685,473
kWh
|
$5,100
-
kW-mo/yr
|
$33,833
-
gal
|
$83,445 | $1,706 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs