ITAC Assessment: UF0329
ITAC logo
ITAC Assessment: UF0329
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Aluminum Automotive Parts
NAICS 331524: Aluminum Foundries (except Die-Casting)
SIC 3365: Aluminum Foundries
Sales Range $50
M
to 100
M
# of Employees 540
Plant Area 209,130
ft2
Annual Production 20,100,000
lb
Production Hrs. Annual 4,080
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $50,201 1,139,263
kWh
Electricity Demand $(-1,028.0) (-232)
kW-mo/yr
Natural Gas $211,054 36,451
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $2,049,841 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.1213: Direct warmest air to combustion intake $211,005 $255,000 n/a - - $211,005
-
MMBtu
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,225 $16,573 n/a $3,532
95,583
kWh
$693
-
kW-mo/yr
- - - -
03 2.4238: Do not use compressed air for personal cooling $11,417 - n/a $11,417
259,475
kWh
- - - - -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $12,931 - n/a $10,394
236,216
kWh
- - $470 - $2,067
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $27,383 $370 n/a $27,401
622,740
kWh
- - $(-18.0) - -
06 2.4133: Use most efficient type of electric motors $9,754 $13,170 n/a $7,197
211,667
kWh
$2,557
-
kW-mo/yr
- - - -
07 3.7221: Improve process control to prevent spills of material $85,198 $48,000 n/a - - $34,789
-
MMBtu
- $50,409 -
08 3.5221: Recycle casting sand $836,208 $1,130,370 n/a $(-3,344.0)
(-98,362)
kWh
$(-996.0)
-
kW-mo/yr
- $57,860 - $782,688
09 3.5248: Separate and recycle scrap metal to foundry or for sale $708,707 $335,000 n/a $(-1,442.0)
(-42,400)
kWh
$(-565.0)
-
kW-mo/yr
$(-34,740.0)
-
MMBtu
- $745,454 -
10 4.212: Adopt in-house material generation $141,821 $165,600 n/a $(-4,952.0)
(-145,656)
kWh
$(-2,717.0)
-
kW-mo/yr
- - - $149,490
11 4.424: Improve space comfort conditioning $1,192 $2,675 n/a - - - $1,192 - -
TOTAL RECOMMENDED $2,049,841 $1,966,758 $50,203
1,139,263
kWh
$(-1,028.0)
-
kW-mo/yr
$211,054
-
MMBtu
$59,504 $795,863 $934,245
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs