Assessment Year | 2003 |
---|---|
Principal Product | resins |
NAICS | 325211: Plastics Material and Resin Manufacturing |
SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
Sales Range | $50 M to 100M |
# of Employees | 87 |
Plant Area |
1,306,805
ft2
|
Annual Production | 65,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $324,731 | 8,110,356 |
kWh
|
$0.040 |
Electricity Demand | $81,224 | 13,706 |
kW-mo/yr
|
$5.93 |
Natural Gas | $563,872 | 150,391 |
MMBtu
|
$3.75 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $209,421 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,414 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1213: Direct warmest air to combustion intake | $136,220 | $60,000 | - | - |
$136,220
-
MMBtu
|
- | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $1,941 | $1,860 |
$1,941
36,632
kWh
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,007 | $3,682 |
$799
19,973
kWh
|
$208
-
kW-mo/yr
|
- | - | |
04 | 2.2111: Install steam trap | $5,631 | $238 | - | - |
$5,631
-
MMBtu
|
- | |
05 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $13,967 | $8,000 |
$11,405
285,120
kWh
|
$2,562
-
kW-mo/yr
|
- | - | |
06 | 2.7124: Make a practice of turning off lights when not needed | $1,783 | - |
$1,783
33,638
kWh
|
- | - | - | |
07 | 4.441: Install automatic packing equipment | $48,872 | $32,000 | - | - | - | $48,872 | |
TOTAL RECOMMENDED | $209,421 | $105,780 |
$15,928
375,363
kWh
|
$2,770
-
kW-mo/yr
|
$141,851
-
MMBtu
|
$48,872 | ||
TOTAL IMPLEMENTED | $7,414 | $238 |
$1,783
33,638
kWh
|
- |
$5,631
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs