ITAC Assessment: UF0326
ITAC logo
ITAC Assessment: UF0326
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product resins
NAICS 325211: Plastics Material and Resin Manufacturing
SIC 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers
Sales Range $50
M
to 100
M
# of Employees 87
Plant Area 1,306,805
ft2
Annual Production 65,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $324,731 8,110,356
kWh
Electricity Demand $81,224 13,706
kW-mo/yr
Natural Gas $563,872 150,391
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $209,421 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,414

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.1213: Direct warmest air to combustion intake $136,220 $60,000 - - $136,220
-
MMBtu
-
02 2.7111: Reduce illumination to minimum necessary levels $1,941 $1,860 $1,941
36,632
kWh
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,007 $3,682 $799
19,973
kWh
$208
-
kW-mo/yr
- -
04 2.2111: Install steam trap $5,631 $238 - - $5,631
-
MMBtu
-
05 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $13,967 $8,000 $11,405
285,120
kWh
$2,562
-
kW-mo/yr
- -
06 2.7124: Make a practice of turning off lights when not needed $1,783 - $1,783
33,638
kWh
- - -
07 4.441: Install automatic packing equipment $48,872 $32,000 - - - $48,872
TOTAL RECOMMENDED $209,421 $105,780 $15,928
375,363
kWh
$2,770
-
kW-mo/yr
$141,851
-
MMBtu
$48,872
TOTAL IMPLEMENTED $7,414 $238 $1,783
33,638
kWh
- $5,631
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs