ITAC Assessment: UF0318
ITAC logo
ITAC Assessment: UF0318
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Thermoformed Planter and Fabric Structures
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 425
Plant Area 505,000
ft2
Annual Production 0
pieces
Production Hrs. Annual 7,488
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $489,792 10,201,153
kWh
Electricity Demand $136,934 54,477
kW-mo/yr
Natural Gas $90,972 93,419
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $139,945 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $120,548

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Other Liquid (haz) Savings Solid Waste (haz) Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,293 $340 $3,311
58,093
kWh
- - - - $(-18.0) -
02 2.3212: Optimize plant power factor $2,400 $12,000 - - $2,400 - - - -
03 2.4133: Use most efficient type of electric motors $14,807 $24,950 $3,057
78,396
kWh
$11,750
-
kW-mo/yr
- - - - -
04 2.7111: Reduce illumination to minimum necessary levels $2,439 $2,619 $2,439
42,783
kWh
- - - - - -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,202 - $1,104
19,365
kWh
- - - - $38 $60
06 2.7135: Install occupancy sensors $1,117 $852 $1,117
28,630
kWh
- - - - - -
07 2.7121: Utilize daylight whenever possible in lieu of artificial light $11,077 $16,791 $5,850
149,992
kWh
$5,527
-
kW-mo/yr
- - - $(-300.0) -
08 2.4231: Reduce the pressure of compressed air to the minimum required $3,449 - $3,449
60,514
kWh
- - - - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $8,037 $13,339 $6,051
155,106
kWh
$1,986
-
kW-mo/yr
- - - - -
10 2.7132: Install timers on light switches in little used areas $2,364 $2,358 $2,364
41,473
kWh
- - - - - -
11 3.7311: Maintain machines to reduce leaks $77,760 $14,000 - - - $77,760
-
gal
- - -
12 4.431: Train operators for maximum operating efficiency $12,000 $8,200 - - - - $12,000
-
lb
- -
TOTAL RECOMMENDED $139,945 $95,449 $28,742
634,352
kWh
$19,263
-
kW-mo/yr
$2,400 $77,760
-
gal
$12,000
-
lb
$(-280.0) $60
TOTAL IMPLEMENTED $120,548 $60,829 $16,972
371,474
kWh
$13,736
-
kW-mo/yr
- $77,760
-
gal
$12,000
-
lb
$20 $60
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Other Liquid (haz) Savings Solid Waste (haz) Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs