Assessment Year | 2003 |
---|---|
Principal Product | Corrugated Cardboard Boxes |
NAICS | 322211: Corrugated and Solid Fiber Box Manufacturing |
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
100,000
ft2
|
Annual Production | 100,000,000
pieces
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $19,985 | 689,131 |
kWh
|
$0.029 |
Electricity Demand | $4,227 | 95 |
kW-mo/yr
|
$44.49 |
Natural Gas | $25,640 | 4,722 |
MMBtu
|
$5.43 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $110,538 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,161 | $11,978 | n/a |
$10,247
353,328
kWh
|
$1,914
-
kW-mo/yr
|
- | - |
02 | 2.7132: Install timers on light switches in little used areas | $4,254 | $1,640 | n/a |
$4,254
114,985
kWh
|
- | - | - |
03 | 2.4133: Use most efficient type of electric motors | $6,925 | $5,839 | n/a |
$4,914
169,451
kWh
|
$2,011
-
kW-mo/yr
|
- | - |
04 | 2.3212: Optimize plant power factor | $5,621 | $15,000 | n/a | - | - | - | $5,621 |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,795 | $7,524 | n/a |
$1,490
51,367
kWh
|
$305
-
kW-mo/yr
|
- | - |
06 | 2.2135: Repair and eliminate steam leaks | $25,640 | $120 | n/a | - | - |
$25,640
-
MMBtu
|
- |
07 | 4.111: Add equipment/ operators to reduce production bottleneck | $6,065 | $10,440 | n/a | - | - | - | $6,065 |
08 | 4.322: Eliminate old stock and modify inventory control | $48,077 | $145,000 | n/a | - | - | - | $48,077 |
TOTAL RECOMMENDED | $110,538 | $197,541 |
$20,905
689,131
kWh
|
$4,230
-
kW-mo/yr
|
$25,640
-
MMBtu
|
$59,763 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs