| Assessment Year | 2003 |
|---|---|
| Principal Product | Roof shingles |
| NAICS | 324122: Asphalt Shingle and Coating Materials Manufacturing |
| SIC | 2952: Asphalt Felts and Coatings |
| Sales Range | $10 M to 50M |
| # of Employees | 115 |
| Plant Area |
250,000
ft2
|
| Annual Production | 3,200,000
pieces
|
| Production Hrs. Annual | 7,800
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $379,031 | 8,064,988 |
kWh
|
$0.047 |
| Electricity Demand | $23,085 | 15,516 |
kW-mo/yr
|
$1.49 |
| Natural Gas | $423,782 | 103,677 |
MMBtu
|
$4.09 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $506,135 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $81,290 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,514 | $1,631 |
$12,014
235,562
kWh
|
$500
-
kW-mo/yr
|
- | - | - | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $1,785 | $1,826 |
$1,713
33,580
kWh
|
$72
-
kW-mo/yr
|
- | - | - | - | - | |
| 03 | 2.2414: Use waste heat from hot flue gases to preheat | $58,093 | $31,024 | - | - |
$58,093
-
MMBtu
|
- | - | - | - | |
| 04 | 2.3212: Optimize plant power factor | $13,902 | $27,000 | - | - | - | - | - | $13,902 | - | |
| 05 | 2.2511: Insulate bare equipment | $7,223 | $973 | - | - |
$7,223
-
MMBtu
|
- | - | - | - | |
| 06 | 2.2424: Use heat in flue gases to preheat products or materials | $19,080 | $34,976 | - | - |
$19,080
-
MMBtu
|
- | - | - | - | |
| 07 | 3.6192: Use a less expensive method of waste removal | $333,770 | $250,000 |
$(-18,857.0)
(-369,750)
kWh
|
$(-3,648.0)
-
kW-mo/yr
|
- |
$356,275
-
lb
|
- | - | - | |
| 08 | 4.651: Install back-up equipment | $57,960 | $109,500 | - | - | - | - | - | - | $57,960 | |
| 09 | 4.444: Install system to collect scrap | $1,808 | $700 | - | - | - | - | $1,808 | - | - | |
| TOTAL RECOMMENDED | $506,135 | $457,630 |
$(-5,130.0)
(-100,608)
kWh
|
$(-3,076.0)
-
kW-mo/yr
|
$84,396
-
MMBtu
|
$356,275
-
lb
|
$1,808 | $13,902 | $57,960 | ||
| TOTAL IMPLEMENTED | $81,290 | $114,630 |
$13,727
269,142
kWh
|
$572
-
kW-mo/yr
|
$7,223
-
MMBtu
|
- | $1,808 | - | $57,960 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs