| Assessment Year | 2002 |
|---|---|
| Principal Product | Control Valves |
| NAICS |
n/a
|
| SIC | 3491: Industrial Valves |
| Sales Range | $10 M to 50M |
| # of Employees | 225 |
| Plant Area |
150,000
ft2
|
| Annual Production | 2,750
pieces
|
| Production Hrs. Annual | 4,420
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $214,096 | 4,440,478 |
kWh
|
$0.048 |
| Electricity Demand | $83,767 | 11,554 |
kW-mo/yr
|
$7.25 |
| Natural Gas | $29,668 | 34,985 |
MMBtu
|
$0.85 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $122,062 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,954 | $340 |
$3,966
50,200
kWh
|
- | - | $(-12.0) | - | |
| 02 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $57,004 | $97,500 |
$57,004
721,571
kWh
|
- | - | - | - | |
| 03 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $27,021 | $84,100 |
$13,761
229,353
kWh
|
$14,095
-
kW-mo/yr
|
- | $(-835.0) | - | |
| 04 | 2.3212: Optimize plant power factor | $2,473 | $10,800 | - | - | - | $2,473 | - | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $16,134 | $32,723 |
$11,788
196,469
kWh
|
$3,524
-
kW-mo/yr
|
$822
-
lb
|
- | - | |
| 06 | 2.7135: Install occupancy sensors | $1,828 | $1,339 |
$1,828
30,466
kWh
|
- | - | - | - | |
| 07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,038 | - |
$710
8,981
kWh
|
- | - | $60 | $268 | |
| 08 | 2.4133: Use most efficient type of electric motors | $10,690 | $19,381 |
$7,740
129,005
kWh
|
$2,950
-
kW-mo/yr
|
- | - | - | |
| 09 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $1,920 | $1,895 | - | - | - | $1,920 | - | |
| TOTAL RECOMMENDED | $122,062 | $248,078 |
$96,797
1,366,045
kWh
|
$20,569
-
kW-mo/yr
|
$822
-
lb
|
$3,606 | $268 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs