Assessment Year | 2002 |
---|---|
Principal Product | Plastic coated paper |
NAICS |
n/a
|
SIC | 2672: Coated and Laminated Paper, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
78,580
ft2
|
Annual Production | 11,000
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $61,009 | 2,493,600 |
kWh
|
$0.024 |
Electricity Demand | $49,001 | 5,495 |
kW-mo/yr
|
$8.92 |
LPG | $8,807 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $98,991 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,341 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7124: Make a practice of turning off lights when not needed | $3,112 | - |
$3,112
61,495
kWh
|
- | - | |
02 | 4.652: Replace existing equipment with more suitable substitutes | $1,516 | $7,336 |
$890
86,908
kWh
|
$626
-
kW-mo/yr
|
- | |
03 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $6,111 | $27,450 |
$2,103
85,850
kWh
|
$4,008
-
kW-mo/yr
|
- | |
04 | 2.2135: Repair and eliminate steam leaks | $9,803 | $75 |
$9,803
193,728
kWh
|
- | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,910 | - |
$3,910
67,475
kWh
|
- | - | |
06 | 2.4133: Use most efficient type of electric motors | $1,207 | $4,727 |
$533
21,627
kWh
|
$674
-
kW-mo/yr
|
- | |
07 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $70,992 | $25,725 | - | - | $70,992 | |
08 | 4.111: Add equipment/ operators to reduce production bottleneck | $2,340 | $1,740 | - | - | $2,340 | |
TOTAL RECOMMENDED | $98,991 | $67,053 |
$20,351
517,083
kWh
|
$5,308
-
kW-mo/yr
|
$73,332 | ||
TOTAL IMPLEMENTED | $18,341 | $7,411 |
$17,715
409,606
kWh
|
$626
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs