Assessment Year | 2002 |
---|---|
Principal Product | Restaurant Furniture |
NAICS |
n/a
|
SIC | 2521: Wood Office Furniture |
Sales Range | $5 M to 10M |
# of Employees | 88 |
Plant Area |
60,000
ft2
|
Annual Production | 200
pieces
|
Production Hrs. Annual | 2,730
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $45,714 | 757,837 |
kWh
|
$0.060 |
Electricity Demand | $20,065 | 2,748 |
kW-mo/yr
|
$7.30 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $222,056 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $219,248 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Primary Raw Material Savings | Primary Product Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $6,946 | $24,472 |
$3,486
49,096
kWh
|
$3,460
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $7,392 | $6,547 |
$4,891
68,889
kWh
|
$2,579
-
kW-mo/yr
|
$(-78.0) | - | - | - | |
03 | 2.8121: Apply for tax-free status for energy purchases | $4,788 | $50 | - | - | $4,788 | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,347 | $350 |
$1,407
13,803
kWh
|
- | $(-60.0) | - | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $587 | - |
$587
5,751
kWh
|
- | - | - | - | - | |
06 | 3.1191: Change procedures / equipment / operating conditions | $46,032 | $4,000 | - | - | - | $46,032 | - | - | |
07 | 3.5316: Contract a wood pallet recycling company | $468 | - | - | - | $468 | - | - | - | |
08 | 4.448: Install automatic part storage / retreval system | $2,808 | $876 | - | - | $2,808 | - | - | - | |
09 | 4.432: Cross-train personnel to avoid lost time | $11,250 | $24,938 | - | - | - | - | $11,250 | - | |
10 | 2.7492: Use proper thickness of insulation on building envelope | $140,438 | $39,000 |
$5,438
53,316
kWh
|
- | - | - | - | $135,000 | |
TOTAL RECOMMENDED | $222,056 | $100,233 |
$15,809
190,855
kWh
|
$6,039
-
kW-mo/yr
|
$7,926 | $46,032 | $11,250 | $135,000 | ||
TOTAL IMPLEMENTED | $219,248 | $99,357 |
$15,809
190,855
kWh
|
$6,039
-
kW-mo/yr
|
$5,118 | $46,032 | $11,250 | $135,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Primary Raw Material Savings | Primary Product Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs