ITAC Assessment: UF0292
ITAC logo
ITAC Assessment: UF0292
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Restaurant Furniture
NAICS
n/a
SIC 2521: Wood Office Furniture
Sales Range $5
M
to 10
M
# of Employees 88
Plant Area 60,000
ft2
Annual Production 200
pieces
Production Hrs. Annual 2,730
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $45,714 757,837
kWh
Electricity Demand $20,065 2,748
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $222,056 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $219,248

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Primary Raw Material Savings Primary Product Savings Increase in Production Savings
01 2.4133: Use most efficient type of electric motors $6,946 $24,472 $3,486
49,096
kWh
$3,460
-
kW-mo/yr
- - - -
02 2.7121: Utilize daylight whenever possible in lieu of artificial light $7,392 $6,547 $4,891
68,889
kWh
$2,579
-
kW-mo/yr
$(-78.0) - - -
03 2.8121: Apply for tax-free status for energy purchases $4,788 $50 - - $4,788 - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,347 $350 $1,407
13,803
kWh
- $(-60.0) - - -
05 2.4231: Reduce the pressure of compressed air to the minimum required $587 - $587
5,751
kWh
- - - - -
06 3.1191: Change procedures / equipment / operating conditions $46,032 $4,000 - - - $46,032 - -
07 3.5316: Contract a wood pallet recycling company $468 - - - $468 - - -
08 4.448: Install automatic part storage / retreval system $2,808 $876 - - $2,808 - - -
09 4.432: Cross-train personnel to avoid lost time $11,250 $24,938 - - - - $11,250 -
10 2.7492: Use proper thickness of insulation on building envelope $140,438 $39,000 $5,438
53,316
kWh
- - - - $135,000
TOTAL RECOMMENDED $222,056 $100,233 $15,809
190,855
kWh
$6,039
-
kW-mo/yr
$7,926 $46,032 $11,250 $135,000
TOTAL IMPLEMENTED $219,248 $99,357 $15,809
190,855
kWh
$6,039
-
kW-mo/yr
$5,118 $46,032 $11,250 $135,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Primary Raw Material Savings Primary Product Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs