ITAC Assessment: UF0287
ITAC logo
ITAC Assessment: UF0287
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Process & Tissue Implants, R&D Orthopedic, Prosthetic & Surg
NAICS
n/a
SIC 3842: Orthopedic, Prosthetic, and Surgical Appliances and Supplies
Sales Range $1
M
to 5
M
# of Employees 370
Plant Area 63,000
ft2
Annual Production 180,733
pieces
Production Hrs. Annual 4,160
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $333,682 5,774,352
kWh
Electricity Demand $68,603 11,611
kW-mo/yr
Natural Gas $43,084 4,625
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $132,485 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $99,409

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings Primary Product Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,092 $920 $784
13,520
kWh
$308
-
kW-mo/yr
- - - -
02 2.7135: Install occupancy sensors $1,260 $2,081 $1,260
21,715
kWh
- - - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $3,637 $16,038 $2,613
45,053
kWh
$1,024
-
kW-mo/yr
- - - -
04 2.7121: Utilize daylight whenever possible in lieu of artificial light $3,729 $10,788 $2,515
43,360
kWh
$1,314
-
kW-mo/yr
- $(-100.0) - -
05 2.6231: Utilize controls to operate equipment only when needed $28,709 $20,000 $28,709
494,983
kWh
- - - - -
06 2.4133: Use most efficient type of electric motors $1,358 - $1,344
23,179
kWh
$14
-
kW-mo/yr
- - - -
07 2.6231: Utilize controls to operate equipment only when needed $9,303 $225 $9,303
117,754
kWh
- - - - -
08 4.448: Install automatic part storage / retreval system $39,000 $5,247 - - - - - $39,000
09 2.8123: Pay utility bills on time $15,147 - - - - - $15,147 -
10 2.7243: Improve air circulation with destratification fans / other methods $29,250 $3,000 - - $29,250 - - -
TOTAL RECOMMENDED $132,485 $58,299 $46,528
759,564
kWh
$2,660
-
kW-mo/yr
$29,250 $(-100.0) $15,147 $39,000
TOTAL IMPLEMENTED $99,409 $29,167 $30,837
531,682
kWh
$322
-
kW-mo/yr
$29,250 - - $39,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs