Assessment Year | 2001 |
---|---|
Principal Product | Process & Tissue Implants, R&D Orthopedic, Prosthetic & Surg |
NAICS |
n/a
|
SIC | 3842: Orthopedic, Prosthetic, and Surgical Appliances and Supplies |
Sales Range | $1 M to 5M |
# of Employees | 370 |
Plant Area |
63,000
ft2
|
Annual Production | 180,733
pieces
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $333,682 | 5,774,352 |
kWh
|
$0.058 |
Electricity Demand | $68,603 | 11,611 |
kW-mo/yr
|
$5.91 |
Natural Gas | $43,084 | 4,625 |
MMBtu
|
$9.32 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $132,485 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $99,409 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,092 | $920 |
$784
13,520
kWh
|
$308
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7135: Install occupancy sensors | $1,260 | $2,081 |
$1,260
21,715
kWh
|
- | - | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,637 | $16,038 |
$2,613
45,053
kWh
|
$1,024
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $3,729 | $10,788 |
$2,515
43,360
kWh
|
$1,314
-
kW-mo/yr
|
- | $(-100.0) | - | - | |
05 | 2.6231: Utilize controls to operate equipment only when needed | $28,709 | $20,000 |
$28,709
494,983
kWh
|
- | - | - | - | - | |
06 | 2.4133: Use most efficient type of electric motors | $1,358 | - |
$1,344
23,179
kWh
|
$14
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.6231: Utilize controls to operate equipment only when needed | $9,303 | $225 |
$9,303
117,754
kWh
|
- | - | - | - | - | |
08 | 4.448: Install automatic part storage / retreval system | $39,000 | $5,247 | - | - | - | - | - | $39,000 | |
09 | 2.8123: Pay utility bills on time | $15,147 | - | - | - | - | - | $15,147 | - | |
10 | 2.7243: Improve air circulation with destratification fans / other methods | $29,250 | $3,000 | - | - | $29,250 | - | - | - | |
TOTAL RECOMMENDED | $132,485 | $58,299 |
$46,528
759,564
kWh
|
$2,660
-
kW-mo/yr
|
$29,250 | $(-100.0) | $15,147 | $39,000 | ||
TOTAL IMPLEMENTED | $99,409 | $29,167 |
$30,837
531,682
kWh
|
$322
-
kW-mo/yr
|
$29,250 | - | - | $39,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs