Assessment Year | 2001 |
---|---|
Principal Product | Truck Accessories |
NAICS |
n/a
|
SIC | 3444: Sheet Metal Work |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
185,000
ft2
|
Annual Production | 24,000
pieces
|
Production Hrs. Annual | 5,304
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $43,083 | 1,263,760 |
kWh
|
$0.034 |
Electricity Demand | $20,493 | 4,494 |
kW-mo/yr
|
$4.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $182,503 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $41,913 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Product Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,550 | $410 |
$1,604
30,258
kWh
|
- | - | $(-54.0) | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,615 | $7,198 |
$6,815
189,304
kWh
|
$1,800
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.8121: Apply for tax-free status for energy purchases | $15,000 | $50 | - | - | - | $15,000 | - | - | |
04 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $11,751 | $25,263 |
$12,001
226,440
kWh
|
- | - | $(-250.0) | - | - | |
05 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $9,972 | $20,010 |
$3,774
104,825
kWh
|
$2,358
-
kW-mo/yr
|
- | - | $3,840 | - | |
06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $2,427 | $8,000 | - | - |
$2,427
-
lb
|
- | - | - | |
07 | 3.5311: Recover and reuse waste material | $1,867 | $534 | - | - |
$1,867
-
lb
|
- | - | - | |
08 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $117,000 | $120,250 | - | - | - | - | - | $117,000 | |
09 | 4.448: Install automatic part storage / retreval system | $14,321 | $4,612 | - | - | - | $14,321 | - | - | |
TOTAL RECOMMENDED | $182,503 | $186,327 |
$24,194
550,827
kWh
|
$4,158
-
kW-mo/yr
|
$4,294
-
lb
|
$29,017 | $3,840 | $117,000 | ||
TOTAL IMPLEMENTED | $41,913 | $20,270 |
$8,419
219,562
kWh
|
$1,800
-
kW-mo/yr
|
$2,427
-
lb
|
$29,267 | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Product Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs