Assessment Year | 2001 |
---|---|
Principal Product | Mobile Phones |
NAICS |
n/a
|
SIC | 3663: Radio and Television Broadcasting and Communications Equipment |
Sales Range | $10 M to 50M |
# of Employees | 500 |
Plant Area |
60,000
ft2
|
Annual Production | 900,000
pieces
|
Production Hrs. Annual | 3,500
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $108,523 | 2,352,872 |
kWh
|
$0.046 |
Electricity Demand | $47,141 | 4,832 |
kW-mo/yr
|
$9.76 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $73,049 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $30,490 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $20,855 | $5,330 |
$16,258
353,458
kWh
|
$4,597
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,175 | $525 |
$278
6,155
kWh
|
$57
-
kW-mo/yr
|
$840 | |
03 | 2.6218: Turn off equipment when not in use | $9,845 | $42,000 |
$9,845
215,416
kWh
|
- | - | |
04 | 2.6125: Keep equipment clean | $9,330 | $12,500 |
$5,465
118,699
kWh
|
$3,865
-
kW-mo/yr
|
- | |
05 | 2.7134: Use photocell controls | $9,635 | $50 | - | - | $9,635 | |
06 | 2.3212: Optimize plant power factor | $1,179 | $416 |
$1,179
25,498
kWh
|
- | - | |
07 | 2.3414: Burn waste to produce steam to drive a steam turbine generator set and use steam exhaust for heat | $416 | $1,895 | - | - | $416 | |
08 | 2.2314: Replace heat treating oven with more efficient unit | $614 | $1,500 | - | - | $614 | |
09 | 3.1182: Make a new by-product | $20,000 | $32,250 | - | - | $20,000 | |
TOTAL RECOMMENDED | $73,049 | $96,466 |
$33,025
719,226
kWh
|
$8,519
-
kW-mo/yr
|
$31,505 | ||
TOTAL IMPLEMENTED | $30,490 | $5,380 |
$16,258
353,458
kWh
|
$4,597
-
kW-mo/yr
|
$9,635 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs