ITAC Assessment: UF0271
ITAC logo
ITAC Assessment: UF0271
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Treated Metal Parts
NAICS
n/a
SIC 3398: Metal Heat Treating
Sales Range $1
M
to 5
M
# of Employees 70
Plant Area 11,450
ft2
Annual Production 20,075
units
Production Hrs. Annual 6,708
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $52,237 1,252,000
kWh
Electricity Demand $37,132 5,122
kW-mo/yr
Natural Gas $23,401 9,450
MMBtu
Other Energy $27,240 1,141
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $38,043 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $26,014

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.8121: Apply for tax-free status for energy purchases $9,184 $50 - - - $9,184
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,027 $2,302 $833
17,711
kWh
$194
-
kW-mo/yr
- -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,439 - $1,439
25,698
kWh
- - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,553 $220 $2,553
31,767
kWh
- - -
05 2.2511: Insulate bare equipment $8,200 $6,910 - - $8,200
-
MMBtu
-
06 2.4133: Use most efficient type of electric motors $4,725 $14,788 $4,725
76,496
kWh
- - -
07 2.7145: Install skylights $1,180 $5,321 $1,180
15,424
kWh
- - -
08 2.4235: Remove or close off unneeded compressed air lines $5,285 $75 $5,285
65,253
kWh
- - -
09 3.6193: Install equipment (eg compactor) to reduce disposal costs $1,210 $7,000 - - - $1,210
10 3.7141: Improve cleaning efficiency by maintaining cleaning system $282 $260 $257
5,487
kWh
$25
-
kW-mo/yr
- -
11 2.2424: Use heat in flue gases to preheat products or materials $2,958 $6,000 $869
18,469
kWh
$2,089
-
kW-mo/yr
- -
TOTAL RECOMMENDED $38,043 $42,926 $17,141
256,305
kWh
$2,308
-
kW-mo/yr
$8,200
-
MMBtu
$10,394
TOTAL IMPLEMENTED $26,014 $23,695 $14,522
215,183
kWh
$2,308
-
kW-mo/yr
- $9,184
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs