| Assessment Year | 2001 |
|---|---|
| Principal Product | Bottled Soft Drinks |
| NAICS |
n/a
|
| SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
| Sales Range | $100 M to 500M |
| # of Employees | 128 |
| Plant Area |
260,000
ft2
|
| Annual Production | 75,000,000
pieces
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $112,598 | 4,045,350 |
kWh
|
$0.028 |
| Electricity Demand | $36,082 | 877 |
kW-mo/yr
|
$41.14 |
| Natural Gas | $86,411 | 34,717 |
MMBtu
|
$2.49 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $24,295 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $198 | $211 | n/a |
$43
1,235
kWh
|
$7
-
kW-mo/yr
|
$148 |
| 02 | 2.8121: Apply for tax-free status for energy purchases | $7,078 | $50 | n/a | - | - | $7,078 |
| 03 | 2.7135: Install occupancy sensors | $580 | $311 | n/a |
$580
16,571
kWh
|
- | - |
| 04 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,077 | $165 | n/a |
$1,077
30,759
kWh
|
- | - |
| 05 | 2.3212: Optimize plant power factor | $2,813 | $4,519 | n/a | - | - | $2,813 |
| 06 | 2.8123: Pay utility bills on time | $69 | $5,256 | n/a | - | - | $69 |
| 07 | 4.126: Install sensors to detect defects | $12,480 | - | n/a | - | - | $12,480 |
| TOTAL RECOMMENDED | $24,295 | $10,512 |
$1,700
48,565
kWh
|
$7
-
kW-mo/yr
|
$22,588 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs