Assessment Year | 2001 |
---|---|
Principal Product | Vinyl coated steel wire closet storage units |
NAICS |
n/a
|
SIC | 2542: Office and Store Fixtures, Partitions, Shelving, and Lockers, Except Wood |
Sales Range | $100 M to 500M |
# of Employees | 800 |
Plant Area |
600,000
ft2
|
Annual Production | 100,000
thousand feet
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $782,188 | 16,596,425 |
kWh
|
$0.047 |
Electricity Demand | $262,080 | 44,047 |
kW-mo/yr
|
$5.95 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $136,749 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $125,878 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,935 | $2,079 |
$5,555
118,113
kWh
|
$2,380
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $945 | $886 |
$247
5,275
kWh
|
$43
-
kW-mo/yr
|
- | - | $655 | - | |
03 | 2.7135: Install occupancy sensors | $6,067 | $3,080 |
$6,067
128,957
kWh
|
- | - | - | - | - | |
04 | 2.8114: Change rate schedules or other changes in utility service | $35,535 | $1,000 | - | - | - | - | - | $35,535 | |
05 | 2.7122: Disconnect ballasts | $4,531 | $22 |
$3,860
82,063
kWh
|
$671
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.8121: Apply for tax-free status for energy purchases | $51,429 | $50 | - | - | - | - | $51,429 | - | |
07 | 2.4133: Use most efficient type of electric motors | $16,668 | $60,448 |
$14,203
302,169
kWh
|
$2,465
-
kW-mo/yr
|
- | - | - | - | |
08 | 3.5316: Contract a wood pallet recycling company | $2,515 | - | - | - | - |
$2,515
-
lb
|
- | - | |
09 | 3.4116: Meter recycled water (to reduce sewer charges) | $5,640 | $1,018 | - | - |
$5,640
-
Tgal
|
- | - | - | |
10 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $700 | $1,895 | - | - | - |
$700
-
lb
|
- | - | |
11 | 4.821: Pay bills on time to avoid late fees | $4,784 | - | - | - | - | - | $4,784 | - | |
TOTAL RECOMMENDED | $136,749 | $70,478 |
$29,932
636,577
kWh
|
$5,559
-
kW-mo/yr
|
$5,640
-
Tgal
|
$3,215
-
lb
|
$56,868 | $35,535 | ||
TOTAL IMPLEMENTED | $125,878 | $67,543 |
$26,072
554,514
kWh
|
$4,888
-
kW-mo/yr
|
- |
$2,515
-
lb
|
$56,868 | $35,535 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs