Assessment Year | 2000 |
---|---|
Principal Product | Residential Lighting Fixtures |
NAICS |
n/a
|
SIC | 3645: Residential Electric Lighting Fixtures |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
300,000
ft2
|
Annual Production | 200,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $138,781 | 1,770,516 |
kWh
|
$0.078 |
Natural Gas | $25,722 | 3,699 |
MMBtu
|
$6.95 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $902,467 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $771,926 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $10,381 | $50 | - | - | $10,381 | |
02 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $128,668 | $650,000 |
$327,974
4,204,572
kWh
|
$(-190,666.0)
-
MMBtu
|
$(-8,640.0) | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,621 | $1,019 |
$1,621
20,809
kWh
|
- | - | |
04 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,873 | $9,381 |
$1,873
24,326
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $793 | $600 |
$793
3,810
kWh
|
- | - | |
06 | 2.2511: Insulate bare equipment | $2,774 | $690 | - |
$2,774
-
MMBtu
|
- | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $226 | - |
$226
2,931
kWh
|
- | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $233 | $220 |
$233
3,224
kWh
|
- | - | |
09 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $702 | - | - | - | $702 | |
10 | 4.111: Add equipment/ operators to reduce production bottleneck | $30,000 | $413 | - | - | $30,000 | |
11 | 4.111: Add equipment/ operators to reduce production bottleneck | $725,196 | $55,800 |
$(-24,804.0)
(-317,995)
kWh
|
- | $750,000 | |
TOTAL RECOMMENDED | $902,467 | $718,173 |
$307,916
3,941,677
kWh
|
$(-187,892.0)
-
MMBtu
|
$782,443 | ||
TOTAL IMPLEMENTED | $771,926 | $58,792 |
$(-21,931.0)
(-287,221)
kWh
|
$2,774
-
MMBtu
|
$791,083 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs