ITAC Assessment: UF0257
ITAC logo
ITAC Assessment: UF0257
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Scrap Metal Processing
NAICS
n/a
SIC 3341: Secondary Smelting and Refining of Nonferrous Metals
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 958,320
ft2
Annual Production 228,000
ton
Production Hrs. Annual 2,210
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $137,795 4,641,266
kWh
Electricity Demand $234,897 47,419
kW-mo/yr
LPG $18,527 1,572
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $150,109 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $36,401

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
01 2.4133: Use most efficient type of electric motors $22,656 $11,141 $12,323
342,321
kWh
$10,333
-
kW-mo/yr
- - -
02 2.6218: Turn off equipment when not in use $10,679 - $10,679
410,610
kWh
- - - -
03 2.8121: Apply for tax-free status for energy purchases $25,945 $50 - - - $25,945 -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,866 $3,305 $1,769
54,807
kWh
$97
-
kW-mo/yr
- - -
05 2.3212: Optimize plant power factor $3,391 $5,450 - - - - $3,391
06 2.7121: Utilize daylight whenever possible in lieu of artificial light $1,363 $6,222 $1,363
35,756
kWh
- - - -
07 3.4155: Meter waste water $10,354 $2,000 - - $10,354
-
lb
- -
08 3.5242: Recover metals from spent solutions and recycle $53,258 $9,785 - - $53,258
-
lb
- -
09 4.514: Re-arrange equipment layout to reduce handling costs $20,597 - - - - $20,597 -
TOTAL RECOMMENDED $150,109 $37,953 $26,134
843,494
kWh
$10,430
-
kW-mo/yr
$63,612
-
lb
$46,542 $3,391
TOTAL IMPLEMENTED $36,401 $18,591 $12,323
342,321
kWh
$10,333
-
kW-mo/yr
$10,354
-
lb
- $3,391
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs