Assessment Year | 2000 |
---|---|
Principal Product | Scrap Metal Processing |
NAICS |
n/a
|
SIC | 3341: Secondary Smelting and Refining of Nonferrous Metals |
Sales Range | $10 M to 50M |
# of Employees | 90 |
Plant Area |
958,320
ft2
|
Annual Production | 228,000
ton
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $137,795 | 4,641,266 |
kWh
|
$0.030 |
Electricity Demand | $234,897 | 47,419 |
kW-mo/yr
|
$4.95 |
LPG | $18,527 | 1,572 |
MMBtu
|
$11.79 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $150,109 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $36,401 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $22,656 | $11,141 |
$12,323
342,321
kWh
|
$10,333
-
kW-mo/yr
|
- | - | - | |
02 | 2.6218: Turn off equipment when not in use | $10,679 | - |
$10,679
410,610
kWh
|
- | - | - | - | |
03 | 2.8121: Apply for tax-free status for energy purchases | $25,945 | $50 | - | - | - | $25,945 | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,866 | $3,305 |
$1,769
54,807
kWh
|
$97
-
kW-mo/yr
|
- | - | - | |
05 | 2.3212: Optimize plant power factor | $3,391 | $5,450 | - | - | - | - | $3,391 | |
06 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,363 | $6,222 |
$1,363
35,756
kWh
|
- | - | - | - | |
07 | 3.4155: Meter waste water | $10,354 | $2,000 | - | - |
$10,354
-
lb
|
- | - | |
08 | 3.5242: Recover metals from spent solutions and recycle | $53,258 | $9,785 | - | - |
$53,258
-
lb
|
- | - | |
09 | 4.514: Re-arrange equipment layout to reduce handling costs | $20,597 | - | - | - | - | $20,597 | - | |
TOTAL RECOMMENDED | $150,109 | $37,953 |
$26,134
843,494
kWh
|
$10,430
-
kW-mo/yr
|
$63,612
-
lb
|
$46,542 | $3,391 | ||
TOTAL IMPLEMENTED | $36,401 | $18,591 |
$12,323
342,321
kWh
|
$10,333
-
kW-mo/yr
|
$10,354
-
lb
|
- | $3,391 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs