Assessment Year | 2000 |
---|---|
Principal Product | Clay and Industrial Sand |
NAICS |
n/a
|
SIC | 3291: Abrasive Products |
Sales Range | $5 M to 10M |
# of Employees | 49 |
Plant Area |
87,000,000
ft2
|
Annual Production | 250,000
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $284,851 | 9,574,150 |
kWh
|
$0.030 |
Electricity Demand | $160,786 | 29,347 |
kW-mo/yr
|
$5.48 |
Natural Gas | $590,800 | 172,925 |
MMBtu
|
$3.42 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $673,600 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $161,328 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $288,146 | $1,200,000 | - |
$288,146
-
kW-mo/yr
|
- | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $140,156 | $26,813 |
$54,730
1,765,533
kWh
|
$85,426
-
kW-mo/yr
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,374 | $3,223 |
$2,410
62,134
kWh
|
$964
-
kW-mo/yr
|
- | - | - | |
04 | 2.2511: Insulate bare equipment | $8,849 | $2,975 | - | - |
$8,849
-
MMBtu
|
- | - | |
05 | 2.4238: Do not use compressed air for personal cooling | $1,420 | $1,212 |
$1,420
30,188
kWh
|
- | - | - | - | |
06 | 2.8121: Apply for tax-free status for energy purchases | $7,529 | $50 | - | - | - | - | $7,529 | |
07 | 3.5311: Recover and reuse waste material | $73,125 | $100,000 | - | - | - |
$73,125
-
lb
|
- | |
08 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $32,500 | $22,020 | - | - | - |
$32,500
-
lb
|
- | |
09 | 4.126: Install sensors to detect defects | $53,501 | $5,465 | - | - | - |
$53,501
-
lb
|
- | |
10 | 4.111: Add equipment/ operators to reduce production bottleneck | $65,000 | $12,000 | - | - | - |
$65,000
-
lb
|
- | |
TOTAL RECOMMENDED | $673,600 | $1,373,758 |
$58,560
1,857,855
kWh
|
$374,536
-
kW-mo/yr
|
$8,849
-
MMBtu
|
$224,126
-
lb
|
$7,529 | ||
TOTAL IMPLEMENTED | $161,328 | $34,273 |
$58,560
1,857,855
kWh
|
$86,390
-
kW-mo/yr
|
$8,849
-
MMBtu
|
- | $7,529 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs