ITAC Assessment: UF0248
ITAC logo
ITAC Assessment: UF0248
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Wheat Flour
NAICS
n/a
SIC 2041: Flour and Other Grain Mill Products
Sales Range $1
M
to 5
M
# of Employees 45
Plant Area 125,000
ft2
Annual Production 440,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $753,672 15,081,770
kWh
Electricity Demand $45,007 27,962
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $142,262 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,563

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
01 4.812: Apply for investment incentives $15,000 $50 - - - $15,000 -
02 2.3212: Optimize plant power factor $3,807 $5,000 - - - - $3,807
03 2.4133: Use most efficient type of electric motors $3,019 $6,796 $2,675
53,634
kWh
$344
-
kW-mo/yr
- - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,859 $600 $3,859
89,097
kWh
- - - -
05 2.4131: Size electric motors for peak operating efficiency $3,292 $6,686 $3,100
62,134
kWh
$192
-
kW-mo/yr
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $4,899 $1,159 $4,686
93,787
kWh
$213
-
kW-mo/yr
- - -
07 2.4238: Do not use compressed air for personal cooling $1,786 $909 $1,786
33,998
kWh
- - - -
08 3.7312: Implement a regular maintenance program to reduce emissions from leaky valves and pipe fittings $7,800 $500 - - $7,800
-
lb
- -
09 4.111: Add equipment/ operators to reduce production bottleneck $98,800 $120,000 - - - $98,800 -
TOTAL RECOMMENDED $142,262 $141,700 $16,106
332,650
kWh
$749
-
kW-mo/yr
$7,800
-
lb
$113,800 $3,807
TOTAL IMPLEMENTED $23,563 $20,491 $11,420
238,863
kWh
$536
-
kW-mo/yr
$7,800
-
lb
- $3,807
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs