Assessment Year | 2000 |
---|---|
Principal Product | Wheat Flour |
NAICS |
n/a
|
SIC | 2041: Flour and Other Grain Mill Products |
Sales Range | $1 M to 5M |
# of Employees | 45 |
Plant Area |
125,000
ft2
|
Annual Production | 440,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $753,672 | 15,081,770 |
kWh
|
$0.050 |
Electricity Demand | $45,007 | 27,962 |
kW-mo/yr
|
$1.61 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $142,262 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $23,563 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.812: Apply for investment incentives | $15,000 | $50 | - | - | - | $15,000 | - | |
02 | 2.3212: Optimize plant power factor | $3,807 | $5,000 | - | - | - | - | $3,807 | |
03 | 2.4133: Use most efficient type of electric motors | $3,019 | $6,796 |
$2,675
53,634
kWh
|
$344
-
kW-mo/yr
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,859 | $600 |
$3,859
89,097
kWh
|
- | - | - | - | |
05 | 2.4131: Size electric motors for peak operating efficiency | $3,292 | $6,686 |
$3,100
62,134
kWh
|
$192
-
kW-mo/yr
|
- | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,899 | $1,159 |
$4,686
93,787
kWh
|
$213
-
kW-mo/yr
|
- | - | - | |
07 | 2.4238: Do not use compressed air for personal cooling | $1,786 | $909 |
$1,786
33,998
kWh
|
- | - | - | - | |
08 | 3.7312: Implement a regular maintenance program to reduce emissions from leaky valves and pipe fittings | $7,800 | $500 | - | - |
$7,800
-
lb
|
- | - | |
09 | 4.111: Add equipment/ operators to reduce production bottleneck | $98,800 | $120,000 | - | - | - | $98,800 | - | |
TOTAL RECOMMENDED | $142,262 | $141,700 |
$16,106
332,650
kWh
|
$749
-
kW-mo/yr
|
$7,800
-
lb
|
$113,800 | $3,807 | ||
TOTAL IMPLEMENTED | $23,563 | $20,491 |
$11,420
238,863
kWh
|
$536
-
kW-mo/yr
|
$7,800
-
lb
|
- | $3,807 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs