ITAC Assessment: UD0501
ITAC logo
ITAC Assessment: UD0501
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product fabric cutting and embroidery
NAICS
n/a
SIC 2326: Men's and Boys' Work Clothing
Sales Range $10
M
to 50
M
# of Employees 550
Plant Area 300,000
ft2
Annual Production 10,000,000
pieces
Production Hrs. Annual 6,100
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $272,985 9,672,919
kWh
Electricity Demand $232,217 20,268
kW-mo/yr
Natural Gas $19,842 4,198
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $52,348 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,536

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
01 2.3212: Optimize plant power factor $9,536 $8,000 - $9,536
-
kW-mo/yr
- -
02 2.2437: Recover waste heat from equipment $3,342 $3,500 - - $3,342
-
MMBtu
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $32,125 $66,000 $14,116
672,333
kWh
$18,009
-
kW-mo/yr
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,333 $7,740 $1,278
60,961
kWh
$2,055
-
kW-mo/yr
- -
05 2.3131: Reschedule plant operations or reduce load to avoid peaks $2,186 - $934
44,549
kWh
$1,252
-
kW-mo/yr
- -
06 3.4116: Meter recycled water (to reduce sewer charges) $1,826 $200 - - - $1,826
-
Tgal
TOTAL RECOMMENDED $52,348 $85,440 $16,328
777,843
kWh
$30,852
-
kW-mo/yr
$3,342
-
MMBtu
$1,826
-
Tgal
TOTAL IMPLEMENTED $9,536 $8,000 - $9,536
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs