ITAC Assessment: UF0244
ITAC logo
ITAC Assessment: UF0244
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Fish
NAICS
n/a
SIC 2091: Canned and Cured Fish and Seafoods
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 50,000
ft2
Annual Production 12,500,000
lb
Production Hrs. Annual 4,500
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $81,508 5,808,910
kWh
Electricity Demand $77,056 9,152
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $26,093 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,014

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Administrative Changes Savings
01 2.8121: Apply for tax-free status for energy purchases $10,455 $50 - - - $10,455
02 2.7124: Make a practice of turning off lights when not needed $527 - $425
30,188
kWh
$102
-
kW-mo/yr
- -
03 2.6218: Turn off equipment when not in use $2,866 $60 $1,953
138,921
kWh
$913
-
kW-mo/yr
- -
04 3.4151: Minimize water usage $9,166 $353 - - $9,166
-
Tgal
-
05 4.652: Replace existing equipment with more suitable substitutes $3,079 - $2,397
16,999
kWh
$576
-
kW-mo/yr
- $106
TOTAL RECOMMENDED $26,093 $463 $4,775
186,108
kWh
$1,591
-
kW-mo/yr
$9,166
-
Tgal
$10,561
TOTAL IMPLEMENTED $23,014 $463 $2,378
169,109
kWh
$1,015
-
kW-mo/yr
$9,166
-
Tgal
$10,455
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs