ITAC Assessment: UF0242
ITAC logo
ITAC Assessment: UF0242
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Sulfuric acid
NAICS
n/a
SIC 2874: Phosphatic Fertilizers
Sales Range $10
M
to 50
M
# of Employees 30
Plant Area 52,000
ft2
Annual Production 930,000
ton
Production Hrs. Annual 8,760
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $648,576 16,214,396
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,102,809 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $38,523

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings Primary Product Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,848 $2,526 $1,848
46,204
kWh
- -
02 2.2437: Recover waste heat from equipment $3,200,000 $17,000,000 $3,200,000
80,592,000
kWh
- -
03 4.111: Add equipment/ operators to reduce production bottleneck $122,360 $141,700 $122,360
3,058,992
kWh
- -
04 2.4133: Use most efficient type of electric motors $20,280 $81,187 $20,280
466,171
kWh
- -
05 2.7135: Install occupancy sensors $1,863 $3,058 $1,863
46,584
kWh
- -
06 2.7124: Make a practice of turning off lights when not needed $1,652 - $1,752
43,800
kWh
$(-100.0) -
07 4.111: Add equipment/ operators to reduce production bottleneck $1,741,926 $6,200,000 $(-1,019,664.0)
(-25,491,000)
kWh
- $2,761,590
08 4.431: Train operators for maximum operating efficiency $12,880 $9,000 $12,880
322,000
kWh
- -
TOTAL RECOMMENDED $5,102,809 $23,437,471 $2,341,319
59,084,751
kWh
$(-100.0) $2,761,590
TOTAL IMPLEMENTED $38,523 $95,771 $38,623
924,759
kWh
$(-100.0) -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Administrative Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs