ITAC Assessment: UF0240
ITAC logo
ITAC Assessment: UF0240
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Shrimp Processing
NAICS
n/a
SIC 2711: Newspapers: Publishing, or Publishing and Printing
Sales Range $50
M
to 100
M
# of Employees 450
Plant Area 90,000
ft2
Annual Production 0
pieces
Production Hrs. Annual 4,420
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $336,730 8,370,164
kWh
Electricity Demand $170,186 21,252
kW-mo/yr
Natural Gas $28,703 4,306
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,508 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,508

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.7111: Reduce illumination to minimum necessary levels $983 - $547
7,620
kWh
$58
-
kW-mo/yr
- - $378
02 2.4231: Reduce the pressure of compressed air to the minimum required $6,086 - $6,086
83,236
kWh
- - - -
03 2.6212: Turn off equipment during breaks, reduce operating time $184 - $126
3,224
kWh
$58
-
kW-mo/yr
- - -
04 3.4151: Minimize water usage $566 $40 - - $566
-
Tgal
- -
05 4.444: Install system to collect scrap $6,689 $12,000 - - $189
-
Tgal
$6,500 -
TOTAL RECOMMENDED $14,508 $12,040 $6,759
94,080
kWh
$116
-
kW-mo/yr
$755
-
Tgal
$6,500 $378
TOTAL IMPLEMENTED $14,508 $12,040 $6,759
94,080
kWh
$116
-
kW-mo/yr
$755
-
Tgal
$6,500 $378
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs