| Assessment Year | 2000 |
|---|---|
| Principal Product | Shrimp Processing |
| NAICS |
n/a
|
| SIC | 2711: Newspapers: Publishing, or Publishing and Printing |
| Sales Range | $50 M to 100M |
| # of Employees | 450 |
| Plant Area |
90,000
ft2
|
| Annual Production | 0
pieces
|
| Production Hrs. Annual | 4,420
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $336,730 | 8,370,164 |
kWh
|
$0.040 |
| Electricity Demand | $170,186 | 21,252 |
kW-mo/yr
|
$8.01 |
| Natural Gas | $28,703 | 4,306 |
MMBtu
|
$6.67 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $14,508 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $14,508 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7111: Reduce illumination to minimum necessary levels | $983 | - |
$547
7,620
kWh
|
$58
-
kW-mo/yr
|
- | - | $378 | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,086 | - |
$6,086
83,236
kWh
|
- | - | - | - | |
| 03 | 2.6212: Turn off equipment during breaks, reduce operating time | $184 | - |
$126
3,224
kWh
|
$58
-
kW-mo/yr
|
- | - | - | |
| 04 | 3.4151: Minimize water usage | $566 | $40 | - | - |
$566
-
Tgal
|
- | - | |
| 05 | 4.444: Install system to collect scrap | $6,689 | $12,000 | - | - |
$189
-
Tgal
|
$6,500 | - | |
| TOTAL RECOMMENDED | $14,508 | $12,040 |
$6,759
94,080
kWh
|
$116
-
kW-mo/yr
|
$755
-
Tgal
|
$6,500 | $378 | ||
| TOTAL IMPLEMENTED | $14,508 | $12,040 |
$6,759
94,080
kWh
|
$116
-
kW-mo/yr
|
$755
-
Tgal
|
$6,500 | $378 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs