ITAC Assessment: UF0236
ITAC logo
ITAC Assessment: UF0236
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Packaged Fruits
NAICS
n/a
SIC 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies
Sales Range $1
M
to 5
M
# of Employees 75
Plant Area 30,000
ft2
Annual Production 140,000
units
Production Hrs. Annual 1,683
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $48,376 349,355
kWh
Electricity Demand $14,987 2,158
kW-mo/yr
Natural Gas $30,667 3,276
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $33,484 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,407

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.8121: Apply for tax-free status for energy purchases $2,582 - - - - $2,582
02 2.4231: Reduce the pressure of compressed air to the minimum required $2,825 - $2,825
14,947
kWh
- - -
03 2.2414: Use waste heat from hot flue gases to preheat $9,777 - - $9,777
-
MMBtu
- -
04 3.5311: Recover and reuse waste material $7,500 - - - $7,500
-
lb
-
05 4.232: Lease equipment instead of purchasing $10,800 - - - - $10,800
TOTAL RECOMMENDED $33,484 - $2,825
14,947
kWh
$9,777
-
MMBtu
$7,500
-
lb
$13,382
TOTAL IMPLEMENTED $5,407 - $2,825
14,947
kWh
- - $2,582
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs