ITAC Assessment: UF0231
ITAC logo
ITAC Assessment: UF0231
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Roofing shingles
NAICS
n/a
SIC 2952: Asphalt Felts and Coatings
Sales Range $50
M
to 100
M
# of Employees 85
Plant Area 200,000
ft2
Annual Production 228
ton
Production Hrs. Annual 6,000
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $203,994 6,525,498
kWh
Electricity Demand $53,088 13,957
kW-mo/yr
Natural Gas $663,296 165,023
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $84,130 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,556

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,328 $4,141 $1,854
59,789
kWh
$474
-
kW-mo/yr
- -
02 2.7232: Replace existing hvac unit with high efficiency model $1,140 $2,650 $657
21,102
kWh
$483
-
kW-mo/yr
- -
03 2.2136: Install / repair insulation on steam lines $1,596 $450 - - $1,596
-
MMBtu
-
04 2.2422: Use waste heat from hot flue gases to generate steam $12,394 $42,085 - - $12,394
-
MMBtu
-
05 2.1233: Analyze flue gas for proper air/fuel ratio $1,198 $1,000 - - $1,198
-
MMBtu
-
06 2.2425: Use flue gases to heat process or service water $62,712 $2,200 - - $62,712
-
MMBtu
-
07 3.5316: Contract a wood pallet recycling company $1,200 - - - - $1,200
08 4.652: Replace existing equipment with more suitable substitutes $1,562 - $1,562
37,222
kWh
- - -
TOTAL RECOMMENDED $84,130 $52,526 $4,073
118,113
kWh
$957
-
kW-mo/yr
$77,900
-
MMBtu
$1,200
TOTAL IMPLEMENTED $5,556 $1,450 $1,562
37,222
kWh
- $2,794
-
MMBtu
$1,200
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs