ITAC Assessment: UF0228
ITAC logo
ITAC Assessment: UF0228
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Plastic Molded Components
NAICS
n/a
SIC 3088: Plastics Plumbing Fixtures
Sales Range $5
M
to 10
M
# of Employees 60
Plant Area 38,000
ft2
Annual Production 180,000,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $94,071 1,806,858
kWh
Electricity Demand $29,530 3,559
kW-mo/yr
Electricity Fees $7,200 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $365,430 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $67,488

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,851 - $4,751
67,995
kWh
$100
-
kW-mo/yr
- - -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $16,958 - $16,643
247,655
kWh
$315
-
kW-mo/yr
- - -
03 2.8121: Apply for tax-free status for energy purchases $9,888 $50 - - $9,888 - -
04 3.6193: Install equipment (eg compactor) to reduce disposal costs $1,660 $955 - - - $1,660
-
lb
-
05 4.445: Install equipment to move product $274,473 $22,390 - - - - $274,473
06 4.624: Hire additional personnel to reduce changeout time $57,600 $1,090,000 - - - - $57,600
TOTAL RECOMMENDED $365,430 $1,113,395 $21,394
315,650
kWh
$415
-
kW-mo/yr
$9,888 $1,660
-
lb
$332,073
TOTAL IMPLEMENTED $67,488 $1,090,050 - - $9,888 - $57,600
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs