Assessment Year | 1999 |
---|---|
Principal Product | Orange and Grapefruit Juice |
NAICS |
n/a
|
SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
Sales Range | $50 M to 100M |
# of Employees | 150 |
Plant Area |
300,000
ft2
|
Annual Production | 25,000,000
lb
|
Production Hrs. Annual | 4,728
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $858,569 | 15,755,276 |
kWh
|
$0.054 |
Electricity Demand | $97,425 | 39,739 |
kW-mo/yr
|
$2.45 |
Electricity Fees | $70,367 | - |
|
- |
Natural Gas | $719,114 | 271,727 |
MMBtu
|
$2.65 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $585,235 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,746 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Energy Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7124: Make a practice of turning off lights when not needed | $1,509 | $60 |
$705
16,999
kWh
|
$804
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,383 | $1,000 |
$4,383
71,805
kWh
|
- | - | - | - | - | $(-1,000.0) | |
03 | 2.2135: Repair and eliminate steam leaks | $9,854 | $4,000 | - | - |
$9,854
-
MMBtu
|
- | - | - | - | |
04 | 2.2437: Recover waste heat from equipment | $51,145 | $40,000 | - | - |
$51,145
-
MMBtu
|
- | - | - | - | |
05 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $400,735 | $1,200,000 |
$478,880
11,679,953
kWh
|
$123,040
-
kW-mo/yr
|
$(-177,185.0)
-
MMBtu
|
- | - | - | $(-24,000.0) | |
06 | 3.5311: Recover and reuse waste material | $14,991 | $2,009 | - | - | - | - |
$14,991
-
gal
|
- | - | |
07 | 3.5311: Recover and reuse waste material | $4,203 | - | - | - | - | - | - |
$4,203
-
lb
|
- | |
08 | 4.232: Lease equipment instead of purchasing | $84,012 | $3,388 | - | - | - | - | - | - | $84,012 | |
09 | 4.446: Automate finishing process | $15,403 | $5,000 | - | - | - |
$15,403
-
MMBtu
|
- | - | - | |
TOTAL RECOMMENDED | $585,235 | $1,255,457 |
$483,968
11,768,757
kWh
|
$123,844
-
kW-mo/yr
|
$(-116,186.0)
-
MMBtu
|
$15,403
-
MMBtu
|
$14,991
-
gal
|
$4,203
-
lb
|
$59,012 | ||
TOTAL IMPLEMENTED | $14,746 | $5,060 |
$5,088
88,804
kWh
|
$804
-
kW-mo/yr
|
$9,854
-
MMBtu
|
- | - | - | $(-1,000.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Energy Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs