ITAC Assessment: UF0218
ITAC logo
ITAC Assessment: UF0218
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Orange and Grapefruit Juice
NAICS
n/a
SIC 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies
Sales Range $50
M
to 100
M
# of Employees 150
Plant Area 300,000
ft2
Annual Production 25,000,000
lb
Production Hrs. Annual 4,728
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $858,569 15,755,276
kWh
Electricity Demand $97,425 39,739
kW-mo/yr
Electricity Fees $70,367 -
Natural Gas $719,114 271,727
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $585,235 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,746

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Energy Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.7124: Make a practice of turning off lights when not needed $1,509 $60 $705
16,999
kWh
$804
-
kW-mo/yr
- - - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,383 $1,000 $4,383
71,805
kWh
- - - - - $(-1,000.0)
03 2.2135: Repair and eliminate steam leaks $9,854 $4,000 - - $9,854
-
MMBtu
- - - -
04 2.2437: Recover waste heat from equipment $51,145 $40,000 - - $51,145
-
MMBtu
- - - -
05 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat $400,735 $1,200,000 $478,880
11,679,953
kWh
$123,040
-
kW-mo/yr
$(-177,185.0)
-
MMBtu
- - - $(-24,000.0)
06 3.5311: Recover and reuse waste material $14,991 $2,009 - - - - $14,991
-
gal
- -
07 3.5311: Recover and reuse waste material $4,203 - - - - - - $4,203
-
lb
-
08 4.232: Lease equipment instead of purchasing $84,012 $3,388 - - - - - - $84,012
09 4.446: Automate finishing process $15,403 $5,000 - - - $15,403
-
MMBtu
- - -
TOTAL RECOMMENDED $585,235 $1,255,457 $483,968
11,768,757
kWh
$123,844
-
kW-mo/yr
$(-116,186.0)
-
MMBtu
$15,403
-
MMBtu
$14,991
-
gal
$4,203
-
lb
$59,012
TOTAL IMPLEMENTED $14,746 $5,060 $5,088
88,804
kWh
$804
-
kW-mo/yr
$9,854
-
MMBtu
- - - $(-1,000.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Energy Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs