| Assessment Year | 1999 |
|---|---|
| Principal Product | Frozen concentrated orange and grapefruit juice |
| NAICS |
n/a
|
| SIC | 2037: Frozen Fruits, Fruit Juices, and Vegetables |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
350,000
ft2
|
| Annual Production | 3,875
Tgal
|
| Production Hrs. Annual | 3,384
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $198,810 | 5,431,419 |
kWh
|
$0.037 |
| Electricity Demand | $27,481 | 15,351 |
kW-mo/yr
|
$1.79 |
| Fuel Oil #6 | $308,826 | 102,260 |
MMBtu
|
$3.02 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $87,159 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,576 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2622: Replace existing chiller with high efficiency model | $50,699 | $251,200 |
$4,149
112,251
kWh
|
$550
-
kW-mo/yr
|
- | - | $46,000 | |
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $11,441 | - | - |
$4,421
-
kW-mo/yr
|
$7,020 | - | - | |
| 03 | 2.1231: Establish burner maintenance schedule for boilers | $6,211 | - | - | - | - |
$7,411
-
MMBtu
|
$(-1,200.0) | |
| 04 | 3.5311: Recover and reuse waste material | $11,243 | $1,800 | - | - | - | - | $11,243 | |
| 05 | 4.652: Replace existing equipment with more suitable substitutes | $5,200 | - | - | - | - | - | $5,200 | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,365 | - |
$1,796
64,771
kWh
|
- | - | - | $569 | |
| TOTAL RECOMMENDED | $87,159 | $253,000 |
$5,945
177,022
kWh
|
$4,971
-
kW-mo/yr
|
$7,020 |
$7,411
-
MMBtu
|
$61,812 | ||
| TOTAL IMPLEMENTED | $8,576 | - |
$1,796
64,771
kWh
|
- | - |
$7,411
-
MMBtu
|
$(-631.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Fuel Oil #6 Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs