| Assessment Year | 1998 |
|---|---|
| Principal Product | Packaging Machinery |
| NAICS |
n/a
|
| SIC | 3544: Special Dies and Tools, Die Sets, Jigs and Fixtures, and Industrial Molds |
| Sales Range | $10 M to 50M |
| # of Employees | 89 |
| Plant Area |
40,000
ft2
|
| Annual Production | 24
pieces
|
| Production Hrs. Annual | 3,900
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $56,464 | 1,094,666 |
kWh
|
$0.052 |
| Electricity Demand | $13,598 | 3,288 |
kW-mo/yr
|
$4.14 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $28,027 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,496 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,805 | $9,240 |
$2,003
38,394
kWh
|
$582
-
kW-mo/yr
|
- | $220 | |
| 02 | 2.7232: Replace existing hvac unit with high efficiency model | $205 | $553 |
$139
2,638
kWh
|
$66
-
kW-mo/yr
|
- | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,496 | $4,720 |
$2,646
41,325
kWh
|
$618
-
kW-mo/yr
|
- | $(-768.0) | |
| 04 | 3.7214: Reduce or eliminate waste | $4,654 | $6,552 |
$2,595
49,824
kWh
|
$619
-
kW-mo/yr
|
$1,440
-
lb
|
- | |
| 05 | 4.111: Add equipment/ operators to reduce production bottleneck | $9,360 | $6,300 | - | - | - | $9,360 | |
| 06 | 2.8121: Apply for tax-free status for energy purchases | $5,907 | $50 | - | - | - | $5,907 | |
| 07 | 4.111: Add equipment/ operators to reduce production bottleneck | $2,600 | $3,000 | - | - | - | $2,600 | |
| TOTAL RECOMMENDED | $28,027 | $30,415 |
$7,383
132,181
kWh
|
$1,885
-
kW-mo/yr
|
$1,440
-
lb
|
$17,319 | ||
| TOTAL IMPLEMENTED | $2,496 | $4,720 |
$2,646
41,325
kWh
|
$618
-
kW-mo/yr
|
- | $(-768.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs