Assessment Year | 1998 |
---|---|
Principal Product | Plywood sheets and treated lumber |
NAICS |
n/a
|
SIC | 2435: Hardwood Veneer and Plywood |
Sales Range | $10 M to 50M |
# of Employees | 268 |
Plant Area |
200,000
ft2
|
Annual Production | 4,849,998
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,232,166 | 27,208,676 |
kWh
|
$0.045 |
Electricity Demand | $378,826 | 50,583 |
kW-mo/yr
|
$7.49 |
Electricity Fees | $(-187,273.0) | - |
|
- |
Wood | $1,604,952 | 1,069,968 |
MMBtu
|
$1.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $222,282 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $189,646 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $9,940 | $10,390 |
$7,821
173,798
kWh
|
$2,119
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $20,997 | $3,200 |
$20,997
411,782
kWh
|
- | - | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $7,422 | $1,215 |
$7,422
165,006
kWh
|
- | - | - | |
04 | 2.3212: Optimize plant power factor | $31,516 | $22,000 | - | - | - | $31,516 | |
05 | 2.2136: Install / repair insulation on steam lines | $3,075 | $471 | - | - |
$3,075
-
MMBtu
|
- | |
06 | 2.3212: Optimize plant power factor | $13,598 | $40,806 |
$13,598
302,169
kWh
|
- | - | - | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $3,914 | $10,000 | - | - | - | $3,914 | |
08 | 3.1291: Eliminate practice of mixing waste streams | $21,300 | $45,000 | - | - | - | $21,300 | |
09 | 4.652: Replace existing equipment with more suitable substitutes | $9,360 | $10,320 | - | - | - | $9,360 | |
10 | 4.611: Begin a practice of predictive / preventative maintenance | $17,160 | $10,000 |
$3,160
69,754
kWh
|
- | - | $14,000 | |
11 | 2.4325: Upgrade conveyors | $84,000 | $10,500 | - | - | - | $84,000 | |
TOTAL RECOMMENDED | $222,282 | $163,902 |
$52,998
1,122,509
kWh
|
$2,119
-
kW-mo/yr
|
$3,075
-
MMBtu
|
$164,090 | ||
TOTAL IMPLEMENTED | $189,646 | $107,687 |
$45,576
957,503
kWh
|
$2,119
-
kW-mo/yr
|
$3,075
-
MMBtu
|
$138,876 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs