ITAC Assessment: UF0201
ITAC logo
ITAC Assessment: UF0201
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Plastic Products
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 70,000
ft2
Annual Production 100,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $149,842 3,664,420
kWh
Electricity Demand $92,529 10,710
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $157,880 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $33,890

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $920 $636 $655
16,120
kWh
$265
-
kW-mo/yr
- -
02 2.4133: Use most efficient type of electric motors $600 $708 $408
9,965
kWh
$192
-
kW-mo/yr
- -
03 2.5113: Use direct flame impingement or infrared processing for chamber type heating $95,103 $238,420 $67,157
1,638,042
kWh
$46,415
-
kW-mo/yr
$(-18,469.0)
-
MMBtu
-
04 2.7145: Install skylights $1,078 $3,000 $1,078
26,377
kWh
- - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $14,996 $2,698 $14,996
199,883
kWh
- - -
06 3.6193: Install equipment (eg compactor) to reduce disposal costs $9,298 $11,000 - - - $9,298
07 3.4111: Use closed cycle process to minimize waste water production $9,439 $26,000 $3,744
49,824
kWh
- - $5,695
08 4.652: Replace existing equipment with more suitable substitutes $10,150 - - - - $10,150
09 2.8121: Apply for tax-free status for energy purchases $16,296 $1,000 - - - $16,296
TOTAL RECOMMENDED $157,880 $283,462 $88,038
1,940,211
kWh
$46,872
-
kW-mo/yr
$(-18,469.0)
-
MMBtu
$41,439
TOTAL IMPLEMENTED $33,890 $8,042 $17,137
252,345
kWh
$457
-
kW-mo/yr
- $16,296
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs