Assessment Year | 1998 |
---|---|
Principal Product | Plastic Products |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 90 |
Plant Area |
70,000
ft2
|
Annual Production | 100,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $149,842 | 3,664,420 |
kWh
|
$0.041 |
Electricity Demand | $92,529 | 10,710 |
kW-mo/yr
|
$8.64 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $157,880 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $33,890 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $920 | $636 |
$655
16,120
kWh
|
$265
-
kW-mo/yr
|
- | - | |
02 | 2.4133: Use most efficient type of electric motors | $600 | $708 |
$408
9,965
kWh
|
$192
-
kW-mo/yr
|
- | - | |
03 | 2.5113: Use direct flame impingement or infrared processing for chamber type heating | $95,103 | $238,420 |
$67,157
1,638,042
kWh
|
$46,415
-
kW-mo/yr
|
$(-18,469.0)
-
MMBtu
|
- | |
04 | 2.7145: Install skylights | $1,078 | $3,000 |
$1,078
26,377
kWh
|
- | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $14,996 | $2,698 |
$14,996
199,883
kWh
|
- | - | - | |
06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $9,298 | $11,000 | - | - | - | $9,298 | |
07 | 3.4111: Use closed cycle process to minimize waste water production | $9,439 | $26,000 |
$3,744
49,824
kWh
|
- | - | $5,695 | |
08 | 4.652: Replace existing equipment with more suitable substitutes | $10,150 | - | - | - | - | $10,150 | |
09 | 2.8121: Apply for tax-free status for energy purchases | $16,296 | $1,000 | - | - | - | $16,296 | |
TOTAL RECOMMENDED | $157,880 | $283,462 |
$88,038
1,940,211
kWh
|
$46,872
-
kW-mo/yr
|
$(-18,469.0)
-
MMBtu
|
$41,439 | ||
TOTAL IMPLEMENTED | $33,890 | $8,042 |
$17,137
252,345
kWh
|
$457
-
kW-mo/yr
|
- | $16,296 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs