ITAC Assessment: UF0187
ITAC logo
ITAC Assessment: UF0187
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Leather belts and watch straps
NAICS
n/a
SIC 3172: Personal Leather Goods, Except Women's Handbags and Purses
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 60,000
ft2
Annual Production 1,000,000
pieces
Production Hrs. Annual 2,210
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $55,807 970,106
kWh
Electricity Demand $16,471 3,432
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,265,343 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $45,354

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Other Liquid (haz) Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $8,078 $31,777 $6,284
108,441
kWh
$1,794
-
kW-mo/yr
- - -
02 2.7135: Install occupancy sensors $763 $820 $763
13,189
kWh
- - - -
03 2.7124: Make a practice of turning off lights when not needed $675 - $675
11,723
kWh
- - - -
04 2.2515: Use optimum thickness insulation $4,626 $14,054 $3,445
59,496
kWh
$1,181
-
kW-mo/yr
- - -
05 2.7232: Replace existing hvac unit with high efficiency model $604 $530 $422
7,327
kWh
$182
-
kW-mo/yr
- - -
06 3.8131: Use water-based adhesives $571 - - - - $571
-
gal
-
07 3.4151: Minimize water usage $1,800 $3,300 - - $1,800
-
Tgal
- -
08 4.111: Add equipment/ operators to reduce production bottleneck $35,426 $50,000 $(-253.0)
4,396
kWh
$(-121.0)
-
kW-mo/yr
- - $35,800
09 4.322: Eliminate old stock and modify inventory control $1,212,800 $23,600 - - - - $1,212,800
TOTAL RECOMMENDED $1,265,343 $124,081 $11,336
204,572
kWh
$3,036
-
kW-mo/yr
$1,800
-
Tgal
$571
-
gal
$1,248,600
TOTAL IMPLEMENTED $45,354 $82,307 $7,128
131,887
kWh
$1,855
-
kW-mo/yr
- $571
-
gal
$35,800
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Other Liquid (haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs