ITAC Assessment: UF0185
ITAC logo
ITAC Assessment: UF0185
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product PVC Pipe
NAICS
n/a
SIC 3084: Plastics Pipe
Sales Range $50
M
to 100
M
# of Employees 120
Plant Area 80,000
ft2
Annual Production 90,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $596,680 15,604,045
kWh
Electricity Demand $209,193 26,219
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $504,801 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $494,931

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $2,893 $4,059 $2,163
56,858
kWh
$730
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,979 $1,725 $7,979
156,506
kWh
- -
03 2.5117: Convert to indirect temperature control system $20,417 $19,200 $20,417
390,094
kWh
- -
04 2.2622: Replace existing chiller with high efficiency model $11,382 $32,000 $8,556
225,088
kWh
$2,826
-
kW-mo/yr
-
05 3.5212: Regrind, reuse, or sell scrap plastic parts $9,870 $31,000 - - $9,870
06 3.4145: Use magnetic technology to treat water $11,000 $43,500 - - $11,000
07 4.113: Install refrigeration system to cool product $420,104 $47,500 - - $420,104
08 2.8121: Apply for tax-free status for energy purchases $21,156 - - - $21,156
TOTAL RECOMMENDED $504,801 $178,984 $39,115
828,546
kWh
$3,556
-
kW-mo/yr
$462,130
TOTAL IMPLEMENTED $494,931 $147,984 $39,115
828,546
kWh
$3,556
-
kW-mo/yr
$452,260
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs