ITAC Assessment: UF0180
ITAC logo
ITAC Assessment: UF0180
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Processed Bell Peppers
NAICS
n/a
SIC 2099: Food Preparations, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 30,000
ft2
Annual Production 700,000
pieces
Production Hrs. Annual 2,600
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $35,444 635,991
kWh
Electricity Demand $13,581 2,950
kW-mo/yr
LPG $320,686 46,904
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $140,412 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,865

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,301 $6,448 $918
17,292
kWh
$383
-
kW-mo/yr
- - - -
02 2.4133: Use most efficient type of electric motors $200 $270 $146
2,638
kWh
$54
-
kW-mo/yr
- - - -
03 2.1233: Analyze flue gas for proper air/fuel ratio $7,698 $1,000 - - $7,698
-
MMBtu
- - -
04 2.2414: Use waste heat from hot flue gases to preheat $2,410 $8,000 - - $2,410
-
MMBtu
- - -
05 2.2123: Insulate feedwater tank $11,355 $36,100 - - $11,355
-
MMBtu
- - -
06 2.2511: Insulate bare equipment $8,872 $270 - - $8,872
-
MMBtu
- - -
07 2.1133: Adjust burners for efficient operation $16,775 - - - $16,775
-
MMBtu
- - -
08 3.5311: Recover and reuse waste material $87,880 - - - $(-31,980.0)
-
MMBtu
$135,000
-
lb
$(-10,140.0) $(-5,000.0)
09 3.1291: Eliminate practice of mixing waste streams $2,127 $3,006 - - - - $2,127 -
10 2.8121: Apply for tax-free status for energy purchases $1,794 - - - - - $1,794 -
TOTAL RECOMMENDED $140,412 $55,094 $1,064
19,930
kWh
$437
-
kW-mo/yr
$15,130
-
MMBtu
$135,000
-
lb
$(-6,219.0) $(-5,000.0)
TOTAL IMPLEMENTED $19,865 $7,988 $1,064
19,930
kWh
$437
-
kW-mo/yr
$16,570
-
MMBtu
- $1,794 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs