| Assessment Year | 1997 |
|---|---|
| Principal Product | Processed Bell Peppers |
| NAICS |
n/a
|
| SIC | 2099: Food Preparations, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
30,000
ft2
|
| Annual Production | 700,000
pieces
|
| Production Hrs. Annual | 2,600
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $35,444 | 635,991 |
kWh
|
$0.056 |
| Electricity Demand | $13,581 | 2,950 |
kW-mo/yr
|
$4.60 |
| LPG | $320,686 | 46,904 |
MMBtu
|
$6.84 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $140,412 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $19,865 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,301 | $6,448 |
$918
17,292
kWh
|
$383
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $200 | $270 |
$146
2,638
kWh
|
$54
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $7,698 | $1,000 | - | - |
$7,698
-
MMBtu
|
- | - | - | |
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $2,410 | $8,000 | - | - |
$2,410
-
MMBtu
|
- | - | - | |
| 05 | 2.2123: Insulate feedwater tank | $11,355 | $36,100 | - | - |
$11,355
-
MMBtu
|
- | - | - | |
| 06 | 2.2511: Insulate bare equipment | $8,872 | $270 | - | - |
$8,872
-
MMBtu
|
- | - | - | |
| 07 | 2.1133: Adjust burners for efficient operation | $16,775 | - | - | - |
$16,775
-
MMBtu
|
- | - | - | |
| 08 | 3.5311: Recover and reuse waste material | $87,880 | - | - | - |
$(-31,980.0)
-
MMBtu
|
$135,000
-
lb
|
$(-10,140.0) | $(-5,000.0) | |
| 09 | 3.1291: Eliminate practice of mixing waste streams | $2,127 | $3,006 | - | - | - | - | $2,127 | - | |
| 10 | 2.8121: Apply for tax-free status for energy purchases | $1,794 | - | - | - | - | - | $1,794 | - | |
| TOTAL RECOMMENDED | $140,412 | $55,094 |
$1,064
19,930
kWh
|
$437
-
kW-mo/yr
|
$15,130
-
MMBtu
|
$135,000
-
lb
|
$(-6,219.0) | $(-5,000.0) | ||
| TOTAL IMPLEMENTED | $19,865 | $7,988 |
$1,064
19,930
kWh
|
$437
-
kW-mo/yr
|
$16,570
-
MMBtu
|
- | $1,794 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs