ITAC Assessment: UF0179
ITAC logo
ITAC Assessment: UF0179
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Automatic Inflators
NAICS
n/a
SIC 3841: Surgical and Medical Instruments and Apparatus
Sales Range $10
M
to 50
M
# of Employees 140
Plant Area 55,000
ft2
Annual Production 25,000
pieces
Production Hrs. Annual 2,385
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $72,103 1,079,132
kWh
Electricity Demand $16,967 3,548
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $47,194 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Primary Raw Material Savings
01 2.7111: Reduce illumination to minimum necessary levels $1,524 $352 $1,226
21,395
kWh
$298
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $11,163 $34,581 $8,999
157,972
kWh
$2,164
-
kW-mo/yr
- -
03 2.7135: Install occupancy sensors $570 $820 $570
9,965
kWh
- - -
04 2.7272: Install heat pipes / raise cooling setpoint $2,876 $3,700 $2,052
36,049
kWh
$824
-
kW-mo/yr
- -
05 3.6193: Install equipment (eg compactor) to reduce disposal costs $3,421 $8,860 - - $3,421 -
06 3.1175: Use a different or recycled raw material $24,578 - - - - $24,578
07 2.8121: Apply for tax-free status for energy purchases $3,062 - - - $3,062 -
TOTAL RECOMMENDED $47,194 $48,313 $12,847
225,381
kWh
$3,286
-
kW-mo/yr
$6,483 $24,578
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs