ITAC Assessment: UF0173
ITAC logo
ITAC Assessment: UF0173
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Veneer boards
NAICS
n/a
SIC 2435: Hardwood Veneer and Plywood
Sales Range $1
M
to 5
M
# of Employees 84
Plant Area 27,000
ft2
Annual Production 310
thousand feet
Production Hrs. Annual 2,080
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $48,657 925,557
kWh
Electricity Demand $19,789 3,668
kW-mo/yr
Fuel Oil #6 $133,593 35,258
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $50,571 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,344

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #6 Savings Administrative Changes Savings Primary Raw Material Savings By-product Production Savings
01 2.4133: Use most efficient type of electric motors $380 $381 $267
4,982
kWh
$113
-
kW-mo/yr
- - - -
02 2.1233: Analyze flue gas for proper air/fuel ratio $3,649 $1,000 - - $3,649
-
MMBtu
- - -
03 2.2113: Repair or replace steam traps $1,315 $138 - - $1,315
-
MMBtu
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $709 $1,839 $606
11,430
kWh
$103
-
kW-mo/yr
- - - -
05 3.1291: Eliminate practice of mixing waste streams $2,228 $2,835 - - - $2,228 - -
06 3.6123: Burn wood by-products for heat $25,000 $120,000 - - $130,000
-
MMBtu
- - $(-105,000.0)
07 4.321: Optimize production lot sizes and inventories $17,290 $10,316 - - - - $17,290 -
TOTAL RECOMMENDED $50,571 $136,509 $873
16,412
kWh
$216
-
kW-mo/yr
$134,964
-
MMBtu
$2,228 $17,290 $(-105,000.0)
TOTAL IMPLEMENTED $5,344 $1,519 $267
4,982
kWh
$113
-
kW-mo/yr
$4,964
-
MMBtu
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Fuel Oil #6 Savings Administrative Changes Savings Primary Raw Material Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs